Tenders due to open for Trans-Borneo Highway

Malaysia’s Trans-Borneo Highway project will see more tenders being offered.
By MJ Woof February 10, 2020 Read time: 1 min
Tenders are opening in Malaysia for further stretches of the Trans-Borneo Highway, with work well underway on the Pan Borneo route - Image courtesy of Lebuhraya Borneo Utara Sdn Bhd

The tender will be issued for construction work on the AH150 Trans-Borneo Highway project during 2020. The tender should be opening in August 2020 if it stays on schedule. Also known as the Pan Borneo Highway and Trans-Kalimantan Highway, the circular AH150 route is an important link for the island of Borneo. This latest tender is for the stretch that connects Sabah and Sarawak in Malaysia with Brunei as well as Indonesia’s Kalimantan Region.

Work for the 40km highway stretch opening to tender will cost some US$144.7 million. The plans will also include building customs facilities at Serundong in Sabah. This will be the third important road project carried out on Borneo, following on from the earlier Pan Borneo Highway work and Sarawak-Sabah Link Road (SSLR).

Related Content

  • Malaysia’s Pan Borneo highway
    March 25, 2019
    A new model is being developed for Malaysia’s landmark Pan Borneo Highway project. The US$7 billion project was originally intended to be carried out under the project delivery partner (PDP) model. However the project is now to be carried out under the turnkey contractor model, managed by the Ministry of Works. This revised plan is expected to reduce construction time. The Pan Borneo Highway is a key project for Malaysia and will help improve transport in Sarawak State and Sabah State. The Pan Borneo highwa
  • Major Malaysian highway projects in hand
    July 24, 2013
    Malaysia’s Lebuh Raya Pantai Timur 2 (LPT2), highway is expected to open for traffic by September 2014. A series of delays have held back work on the 184km highway, although the 72km Bukit Besi-Kuala Terengganu section has been open since the third quarter of 2011. Some of the delays can be attributed to price increases in the cost of materials, which caused problems for contractors involved with the project. Work is ongoing at present on the section of highway from Bukit Mempusi-Kemamn's Felda Kerteh 6. Me
  • Malaysia’s major highway project
    July 13, 2020
    A safety system contract has been awarded for Malaysia’s major highway project.
  • Pan-Borneo highway upgrade in discussion
    June 6, 2013
    Plans are being worked on for an upgrade to the 2,083km Pan—Borneo highway. The Malaysian Government is discussing options with regard to the highway, which connects Sarawak's Sematan, with Brunei and Sabah's Serudung. The work is expected to require five years to be carried out and would also include constructing link roads. The project is expected to cost in the order of US$3.23 billion and Malaysian contractor Naim Holdings is amongst the leading bidders for the work. The highway project forms part of an