Sunderland’s Northern Spire bridge opens

Sunderland’s Northern Spire bridge with its 105m-high central A-frame pylon opens to traffic today after a four-month delay because of poor weather. The bridge opened for pedestrians and cyclists yesterday after three Sunderland-built Nissan vehicles first crossed the bridge during a ceremony to mark completion of the project. Work began in May 2015 and the bridge has been built within its allocated €129 million budget. However, poor weather conditions pushed back the opening of the bridge from this past
August 28, 2018 Read time: 2 mins
Aspiring spire: The Northern Spire’s 105m-high central A-frame pylon highlights the Sunderland project

Sunderland’s Northern Spire bridge with its 105m-high central A-frame pylon opens to traffic today after a four-month delay because of poor weather.

The bridge opened for pedestrians and cyclists yesterday after three Sunderland-built Nissan vehicles first crossed the bridge during a ceremony to mark completion of the project.

Work began in May 2015 and the bridge has been built within its allocated €129 million budget.

However, poor weather conditions pushed back the opening of the bridge from this past spring, said Mark Jackson, Sunderland City’s head of infrastructure and transportation. Particularly affected was the painting of the pylon, which needed very still, dry, calm conditions, both for the painting and the use of high-level working platforms required by the painting team.

The 336m-long two-span cable-stayed bridge across the River Wear has four vehicle lanes, as well as dedicated cycle and pedestrian routes. The steel and concrete bridge is part of 2.8km of new road layout.

Steel specialist Victor Buyck spent a year fabricating the pylon at its canal-side yard in Ghent, Belgium. Apart from the 1,550tonnes tonnes of steel, around 550tonnes of concrete went into making the pylon that, because of its size, had to be constructed in the open air. It was barged across the often-treacherous North Sea to Sunderland.

World Highways has been following construction of the project, including the manufacturing, transport and raising of the main pylon.
http://www.worldhighways.com/categories/road-highway-structures/features/sunderlands-new-wear-crossing-takes-shape/

The construction contract was awarded to FVB, an international joint venture set up by Farrans Construction and Victor Buyck Steel Construction. Farrans Construction operates as a building and civil engineering contractor across the UK and Ireland. Victor Buyck, based in Belgium, is one of Europe's major structural steelwork contractors, specialising in steel bridges.

FVB has been supported by its design team led by Buro Happold Engineering and Roughan & O'Donovan. Independent checker has been Ramboll.

Related Content

  • Sunderland’s sliding bridge slips across the Wear
    October 26, 2016
    Slowly but surely, a 2,500 tonne section of a new bridge deck was eased out from the banks of the River Wear near Sunderland in northern England. It now straddles the water, pointing towards the opposite bank which it will eventually reach after another sliding operation next year likely. The project to build the New Wear Crossing is now half way through with the first half of the steel deck bridge poised mid-river. Completion of the bridge is expected in the spring of 2018. This month, hydraulic jack
  • Launch soon for the Sunderland Bridge’s deck across the Wear
    March 24, 2017
    The team constructing the New Wear Crossing near the English city of Sunderland is preparing for the final launch of the 300m bridge deck. In recent weeks, the legs of the 100m-tall centrepiece have been secured to the foundations within the riverbed and most of the rigging used to raise it into place has been removed. While the bridge deck was being painted, the bottoms of both pylon legs were filled with 175tonnes of concrete, The next major process will be to slowly pull the bridge deck out acr
  • Europe closes in on the crossings
    September 27, 2017
    The Mersey Gateway bridge project off England’s west coast passed a milestone recently with the first joining of two of the deck sections. The key segments, as the sections are called, link the north approach viaduct to the north pylon deck span and are the first of four deck-joins scheduled for this summer. In total, there are five sections of bridge deck and approach roads that need to be joined.
  • Bridges in Sunderland and Poland are being slid into place
    February 6, 2017
    Sunderland sees a bridge slide into place and two bridges inch their way across a Polish highway Slowly but surely, a 2,500 tonne section of a new bridge deck was eased out from the banks of the River Wear near Sunderland in northern England. It now straddles the water, pointing towards the opposite bank which it will eventually reach after another sliding operation likely to take place next year. The project to build the New Wear Crossing is now halfway through with the first half of the steel deck b