Sunderland’s Northern Spire bridge opens

Sunderland’s Northern Spire bridge with its 105m-high central A-frame pylon opens to traffic today after a four-month delay because of poor weather. The bridge opened for pedestrians and cyclists yesterday after three Sunderland-built Nissan vehicles first crossed the bridge during a ceremony to mark completion of the project. Work began in May 2015 and the bridge has been built within its allocated €129 million budget. However, poor weather conditions pushed back the opening of the bridge from this past
August 28, 2018 Read time: 2 mins
Aspiring spire: The Northern Spire’s 105m-high central A-frame pylon highlights the Sunderland project

Sunderland’s Northern Spire bridge with its 105m-high central A-frame pylon opens to traffic today after a four-month delay because of poor weather.

The bridge opened for pedestrians and cyclists yesterday after three Sunderland-built Nissan vehicles first crossed the bridge during a ceremony to mark completion of the project.

Work began in May 2015 and the bridge has been built within its allocated €129 million budget.

However, poor weather conditions pushed back the opening of the bridge from this past spring, said Mark Jackson, Sunderland City’s head of infrastructure and transportation. Particularly affected was the painting of the pylon, which needed very still, dry, calm conditions, both for the painting and the use of high-level working platforms required by the painting team.

The 336m-long two-span cable-stayed bridge across the River Wear has four vehicle lanes, as well as dedicated cycle and pedestrian routes. The steel and concrete bridge is part of 2.8km of new road layout.

Steel specialist Victor Buyck spent a year fabricating the pylon at its canal-side yard in Ghent, Belgium. Apart from the 1,550tonnes tonnes of steel, around 550tonnes of concrete went into making the pylon that, because of its size, had to be constructed in the open air. It was barged across the often-treacherous North Sea to Sunderland.

World Highways has been following construction of the project, including the manufacturing, transport and raising of the main pylon.
http://www.worldhighways.com/categories/road-highway-structures/features/sunderlands-new-wear-crossing-takes-shape/

The construction contract was awarded to FVB, an international joint venture set up by Farrans Construction and Victor Buyck Steel Construction. Farrans Construction operates as a building and civil engineering contractor across the UK and Ireland. Victor Buyck, based in Belgium, is one of Europe's major structural steelwork contractors, specialising in steel bridges.

FVB has been supported by its design team led by Buro Happold Engineering and Roughan & O'Donovan. Independent checker has been Ramboll.

Related Content

  • Cleveland Bridge on A1 project in the UK
    February 7, 2017
    Cleveland Bridge UK has delivered a significant upgrade project on the A1 in North Yorkshire, England, with the fabrication and installation of eight bridges. Using British-made steel, the 20-month project was completed with the installation of the 53m Fort Overbridge. The work was carried out on behalf of Highways England’s principal contractor on the A1 scheme, a Carillion and Morgan Sindall joint venture. The A1 Leeming to Barton upgrade is replacing the dual carriageway with a three-lane motorw
  • Svevia to renovate Sweden's Smögen Bridge
    March 22, 2023
    The seven-pillar box-beam bridge will remain open but with limited traffic during the repairs.
  • CDE unveils single chassis M5500 sand wash plant
    March 7, 2017
    CDE’s new North America market-orientated M5500 sand washing plant is able to produce up to an impressive 550tonnes/hour of washed materials on a single chassis. The M5500 model on show at CONEXPO-CON/AGG 2017 was sold to a major US frac sand supplier only last week.
  • €14.47bn to fix England and Wales local road network, ALARM Survey claims
    April 3, 2014
    The 19th Annual Local Authority Road Maintenance (ALARM) Survey published today reports that the estimated cost to get England and Wales’ local road network back into reasonable condition has increased to €14.47 billion (£12 billion) from €12.06 billion (£10.5 billion) in 2013. For the second year in a row, more than two million potholes (2,010,749) were filled in England and Wales over the course of the previous year.