Sunderland’s Northern Spire bridge opens

Sunderland’s Northern Spire bridge with its 105m-high central A-frame pylon opens to traffic today after a four-month delay because of poor weather. The bridge opened for pedestrians and cyclists yesterday after three Sunderland-built Nissan vehicles first crossed the bridge during a ceremony to mark completion of the project. Work began in May 2015 and the bridge has been built within its allocated €129 million budget. However, poor weather conditions pushed back the opening of the bridge from this past
August 28, 2018 Read time: 2 mins
Aspiring spire: The Northern Spire’s 105m-high central A-frame pylon highlights the Sunderland project

Sunderland’s Northern Spire bridge with its 105m-high central A-frame pylon opens to traffic today after a four-month delay because of poor weather.

The bridge opened for pedestrians and cyclists yesterday after three Sunderland-built Nissan vehicles first crossed the bridge during a ceremony to mark completion of the project.

Work began in May 2015 and the bridge has been built within its allocated €129 million budget.

However, poor weather conditions pushed back the opening of the bridge from this past spring, said Mark Jackson, Sunderland City’s head of infrastructure and transportation. Particularly affected was the painting of the pylon, which needed very still, dry, calm conditions, both for the painting and the use of high-level working platforms required by the painting team.

The 336m-long two-span cable-stayed bridge across the River Wear has four vehicle lanes, as well as dedicated cycle and pedestrian routes. The steel and concrete bridge is part of 2.8km of new road layout.

Steel specialist Victor Buyck spent a year fabricating the pylon at its canal-side yard in Ghent, Belgium. Apart from the 1,550tonnes tonnes of steel, around 550tonnes of concrete went into making the pylon that, because of its size, had to be constructed in the open air. It was barged across the often-treacherous North Sea to Sunderland.

World Highways has been following construction of the project, including the manufacturing, transport and raising of the main pylon.
http://www.worldhighways.com/categories/road-highway-structures/features/sunderlands-new-wear-crossing-takes-shape/

The construction contract was awarded to FVB, an international joint venture set up by Farrans Construction and Victor Buyck Steel Construction. Farrans Construction operates as a building and civil engineering contractor across the UK and Ireland. Victor Buyck, based in Belgium, is one of Europe's major structural steelwork contractors, specialising in steel bridges.

FVB has been supported by its design team led by Buro Happold Engineering and Roughan & O'Donovan. Independent checker has been Ramboll.

Related Content

  • Montreal’s Champlain Bridge opens but late and over-budget
    June 27, 2019
    Montreal’s US$3.5-billion, 3.4km-long Samuel de Champlain Bridge has opened after four years of construction and months of delays, according to Canadian media reports. Work is continuing on the cycle and pedestrian paths and eventually a light-rail train will run down the middle of the six lane bridge over the St. Lawrence River. The new structure has a life-span of 125 years and runs alongside its namesake Champlain Bridge, a steel truss cantilever that opened in 1962 which will be demolished. Accord
  • Mersey Gateway Project reaches half-way point across the Mersey
    March 10, 2017
    The Mersey Gateway project in England has passed a significant milestone, with over half of the main bridge deck stretching across the River Mersey. Work to install stay cables on the main bridge also passed a key point, with installation of the 31st 150m long cable – the halfway point for stay cable installations on the pylon. When complete, 146 stay cables will support the 1km-long reinforced concrete bridge, with a combined load-bearing weight of more than 53,000tonnes. “We’re now more than 50
  • Rapid International supplies Collier Group with a batching plant
    December 7, 2017
    Rapid International has supplied Collier Group, based in Fife, Scotland, with the contractor’s first bespoke static concrete batching plant. Rapid, based in County Armagh, Northern Ireland, said that the batching plant was installed at Collier’s Goathill Quarry in Fife. Collier Group’s plant is built on a slope and includes five 4m-wide 80tonne capacity aggregate bins as well as three 160tonne capacity silos. The silos are accessed from the upper ground level, along with filler hoses to fill the four 2500
  • Turkmenistan’s new bridge features novel waterproofing
    November 8, 2017
    Turkmenistan’s new bridge is benefiting from a novel sealing system that will optimise working life as well as maximising safety. A novel waterproofing solution is being utilised for the Turkmenabat - Farap Bridge in Turkmenistan. The project is of note as the structure is the longest metal span bridge in Central Asia. The client for the project is the state-owned firm Turkmenavtohowayollary, while the general contractor is Altcom Road Construction and the consultant engineer is Soyuztransproekt. Stirling