SSL settles legal issues, Champlain Bridge to open December 21

Montreal will get its new Champlain Bridge just before Christmas, a date agreed upon by the Canadian government and the SNC-Lavalin-led consortium. The agreement settles an outstanding lawsuit that the Consortium had filed regarding costs increases of around US$186.5 million relating to the transportation of oversized parts and delays to the bridge's construction, according to media reports. Last month SNC-Lavalin, head of the Signature on the Saint-Laurent Group (SSL), had said that the bridge over the
April 18, 2018 Read time: 2 mins
Merry Christmas to Montreal: Champlain Bridge replacement opens in December

Montreal will get its new Champlain Bridge just before Christmas, a date agreed upon by the Canadian government and the SNC-Lavalin-led consortium.

The agreement settles an outstanding lawsuit that the Consortium had filed regarding costs increases of around US$186.5 million relating to the transportation of oversized parts and delays to the bridge's construction, according to media reports.

Last month SNC-Lavalin, head of the Signature on the Saint-Laurent Group (SSL), had said that the bridge over the St Lawrence River and Seaway canal would open in December but gave no date. The December 21 date it newly three weeks later than planned.

Failure to open the 3.4km-long bridge to vehicular traffic on time means the consortium would face stiff fines, according to media reports: around $77,500 a day for the first seven days followed by $310,000 per day.

No details of the settlement were released.

Cost of the entire 6km corridor project is set at US$3.3 billion of which around $1.8 billion is for construction of the bridge, approach roads and highway adjustments.

The federal Canadian government signed a public-private partnership deal with the SNC-Lavalin consortium Signature on the Saint-Laurent Group in mid-2015 for the group to design, build, finance and maintain the New Champlain Bridge Corridor project. SNC-Lavalin is a 50% partner in SSL which will operate and maintain the bridge until October 2049. Other SSL partners are Hochtief, Flatiron, Dragados Canada and Grupo ACS.

Meanwhile, SSL entered into a date-certain, fixed-priced contract with a construction joint venture of which SNC-Lavalin is again a 50% partner.

The new bridge has six vehicle lanes plus two lanes running in the middle of the bridge for electric public transit trains. The bridge runs from the Ile des Soeurs to Brossard, immediately downstream from the existing Champlain Bridge.

Every year, around 50 million vehicles cross the old bridge, Canada’s most heavily travelled bridge and a major route for traffic to and from the US. Construction of the existing steel truss cantilever bridge, as well as accompanying approaches and the Bonaventure Expressway, started in 1957 and finished in 1962. Of the old 14.5km-long complex, the bridge is 7.4km.

Related Content

  • African Development Bank funds road to Africa’s largest wind farm
    February 20, 2014
    Shem Oirere discusses a new road connecting with a wind farm development in Kenya The African Development Bank will provide 45% of the funding needed for the rehabilitation and rebuilding of a new 200km road which leads to Africa's largest wind farm project, located in northern Kenya. The bank said the $13.5 million grant for rehabilitation of the existing Laisamis – Ngurunit – llaut - South Horr – Loyangalani road- will be provided by the Government of the Netherlands. The bank says works on the road will
  • China opens record-breaking bridge
    February 22, 2012
    China has opened the world's longest bridge over water, the 41.58km Jiaozhou Bay Bridge, which is said to have cost well over US$2 billion to build. It links the eastern port city of Qingdao to Huangdao Island across Jiaozhou Bay and is 4km longer than the previous longest bridge over water, the Lake Pontchartrain Causeway in Louisiana, USA. Opened in June, 2011 after four years of construction, the link is expected to carry some 30,000 vehicle/day and will reduce travel time by 30 minutes, although it is o
  • China opens record-breaking bridge
    May 8, 2012
    China has opened the world's longest bridge over water, the 41.58km Jiaozhou Bay Bridge, which is said to have cost well over US$2 billion to build. It links the eastern port city of Qingdao to Huangdao Island across Jiaozhou Bay and is 4km longer than the previous longest bridge over water, the Lake Pontchartrain Causeway in Louisiana, USA. Opened in June, 2011 after four years of construction, the link is expected to carry some 30,000 vehicle/day and will reduce travel time by 30 minutes, although it is o
  • $1.9 billion for Oregon-Washington bridge replacement
    May 20, 2025
    A further $1.9 billion is needed for the Oregon-Washington bridge replacement.