SSL settles legal issues, Champlain Bridge to open December 21

Montreal will get its new Champlain Bridge just before Christmas, a date agreed upon by the Canadian government and the SNC-Lavalin-led consortium. The agreement settles an outstanding lawsuit that the Consortium had filed regarding costs increases of around US$186.5 million relating to the transportation of oversized parts and delays to the bridge's construction, according to media reports. Last month SNC-Lavalin, head of the Signature on the Saint-Laurent Group (SSL), had said that the bridge over the
April 18, 2018 Read time: 2 mins
Merry Christmas to Montreal: Champlain Bridge replacement opens in December

Montreal will get its new Champlain Bridge just before Christmas, a date agreed upon by the Canadian government and the SNC-Lavalin-led consortium.

The agreement settles an outstanding lawsuit that the Consortium had filed regarding costs increases of around US$186.5 million relating to the transportation of oversized parts and delays to the bridge's construction, according to media reports.

Last month SNC-Lavalin, head of the Signature on the Saint-Laurent Group (SSL), had said that the bridge over the St Lawrence River and Seaway canal would open in December but gave no date. The December 21 date it newly three weeks later than planned.

Failure to open the 3.4km-long bridge to vehicular traffic on time means the consortium would face stiff fines, according to media reports: around $77,500 a day for the first seven days followed by $310,000 per day.

No details of the settlement were released.

Cost of the entire 6km corridor project is set at US$3.3 billion of which around $1.8 billion is for construction of the bridge, approach roads and highway adjustments.

The federal Canadian government signed a public-private partnership deal with the SNC-Lavalin consortium Signature on the Saint-Laurent Group in mid-2015 for the group to design, build, finance and maintain the New Champlain Bridge Corridor project. SNC-Lavalin is a 50% partner in SSL which will operate and maintain the bridge until October 2049. Other SSL partners are Hochtief, Flatiron, Dragados Canada and Grupo ACS.

Meanwhile, SSL entered into a date-certain, fixed-priced contract with a construction joint venture of which SNC-Lavalin is again a 50% partner.

The new bridge has six vehicle lanes plus two lanes running in the middle of the bridge for electric public transit trains. The bridge runs from the Ile des Soeurs to Brossard, immediately downstream from the existing Champlain Bridge.

Every year, around 50 million vehicles cross the old bridge, Canada’s most heavily travelled bridge and a major route for traffic to and from the US. Construction of the existing steel truss cantilever bridge, as well as accompanying approaches and the Bonaventure Expressway, started in 1957 and finished in 1962. Of the old 14.5km-long complex, the bridge is 7.4km.

Related Content

  • India pushing ahead with infrastructure projects
    July 4, 2012
    Despite the economic downturn, India looks to be pressing ahead with its major infrastructure projects to further boost its incredible growth. Patrick Smith reports India, which like most countries has been affected by the current economic climate, although not to the same extent, is pressing ahead with its ambitious highway construction plans. Each week new projects are completed, started or awarded as the nation seeks to improve its transportation requirements. These are needed to meet the aspirations of
  • Parsons’ Ohio River Bridges East End Crossing Project opens
    January 3, 2017
    In the US, the Ohio River Bridges East End Crossing—now named Lewis and Clark Bridge—opened to traffic in mid-December.
  • Slovakia opens up more D1 motorway sections to tender
    June 9, 2015
    Slovakia’s national motorway company NDS has put out to tender two sections of the D1 motorway near Presov and Kosice. Both tenders have been published in the Official Journal of the European Union, with bid submission deadlines set for June 29. The first section is the south-west D1 by-pass of Presov at nearly 8km long, including the construction of a 2km duel-tube road tunnel Presov and estimated to cost €443.4 million. The second section is the 14.5km-long D1 Budimir to Bidovce stretch, with cost
  • Finnish Motorway Finally finished: Finland's M1
    July 23, 2012
    It has taken a long time to complete, but a vital motorway link is open to traffic as Heikki Harri reports After almost 50 years of construction, the M1 motorway linking Helsinki, the Finnish capital city and Turku, the country's old capital in the southwest, is finally completed. It did not take all 50 years of construction but the first section from Helsinki towards the west was constructed in the mid -1960s. Then there was a pause until mid-1990s when the works resumed section by section. The final sect