SSL settles legal issues, Champlain Bridge to open December 21

Montreal will get its new Champlain Bridge just before Christmas, a date agreed upon by the Canadian government and the SNC-Lavalin-led consortium. The agreement settles an outstanding lawsuit that the Consortium had filed regarding costs increases of around US$186.5 million relating to the transportation of oversized parts and delays to the bridge's construction, according to media reports. Last month SNC-Lavalin, head of the Signature on the Saint-Laurent Group (SSL), had said that the bridge over the
April 18, 2018 Read time: 2 mins
Merry Christmas to Montreal: Champlain Bridge replacement opens in December

Montreal will get its new Champlain Bridge just before Christmas, a date agreed upon by the Canadian government and the SNC-Lavalin-led consortium.

The agreement settles an outstanding lawsuit that the Consortium had filed regarding costs increases of around US$186.5 million relating to the transportation of oversized parts and delays to the bridge's construction, according to media reports.

Last month SNC-Lavalin, head of the Signature on the Saint-Laurent Group (SSL), had said that the bridge over the St Lawrence River and Seaway canal would open in December but gave no date. The December 21 date it newly three weeks later than planned.

Failure to open the 3.4km-long bridge to vehicular traffic on time means the consortium would face stiff fines, according to media reports: around $77,500 a day for the first seven days followed by $310,000 per day.

No details of the settlement were released.

Cost of the entire 6km corridor project is set at US$3.3 billion of which around $1.8 billion is for construction of the bridge, approach roads and highway adjustments.

The federal Canadian government signed a public-private partnership deal with the SNC-Lavalin consortium Signature on the Saint-Laurent Group in mid-2015 for the group to design, build, finance and maintain the New Champlain Bridge Corridor project. SNC-Lavalin is a 50% partner in SSL which will operate and maintain the bridge until October 2049. Other SSL partners are Hochtief, Flatiron, Dragados Canada and Grupo ACS.

Meanwhile, SSL entered into a date-certain, fixed-priced contract with a construction joint venture of which SNC-Lavalin is again a 50% partner.

The new bridge has six vehicle lanes plus two lanes running in the middle of the bridge for electric public transit trains. The bridge runs from the Ile des Soeurs to Brossard, immediately downstream from the existing Champlain Bridge.

Every year, around 50 million vehicles cross the old bridge, Canada’s most heavily travelled bridge and a major route for traffic to and from the US. Construction of the existing steel truss cantilever bridge, as well as accompanying approaches and the Bonaventure Expressway, started in 1957 and finished in 1962. Of the old 14.5km-long complex, the bridge is 7.4km.

Related Content

  • Canada’s toll Highway 407 extension east of Toronto opens
    June 21, 2016
    A US$780 million eastward extension to Toronto’s major toll highway 407 has opened after four years of construction. Work on 407 East Phase 1 project – which also included construction of the smaller Highway 412 – involved building more than 148 lane-kilometres and 11 interchanges. The 22km road stretches from Brock Road in the town of Pickering to Harmony Road in the city of Oshawa. Highway 412 is a 10km north-south road that connects Highway 407 to Highway 401. Travel on the toll road will be free u
  • Golden opportunities in the MINT - Mexico, Indonesia, Nigeria, Turkey
    May 21, 2015
    Mexico, Indonesia, Nigeria, Turkey – Global Report offers up some food for thought about where smart money might be headed within the next several years – David Arminas writes China’s rate of growth may be slowing down, but other South East Asian companies are being quick to offer alternate investment opportunities, notably Indonesia. Nigeria, too, has had issues with security of investment. But there are signs that the government may be getting serious at last about tightening up rules and regulation
  • More on the Newmarket Viaduct replacement
    June 15, 2012
    When it was completed in 1965 – just six years after the Auckland Harbour Bridge – the six-lane Newmarket Viaduct with its tall, slender piers was something of an engineering wonder, the first of its kind in the Southern Hemisphere. Forty years on it had become a much-maligned contributor to Auckland’s chronic traffic congestion, too weak seismically to withstand the heaviest loaded trucks let alone a severe earthquake, so narrow in the shoulders that any accident stopped traffic flow and made it difficult
  • VIDEO: Virginia approves Hampton Roads Bridge Tunnel expansion
    December 12, 2016
    The US state of Virginia has approved a US$4 billion project to expand the Hampton Roads Bridge Tunnel close to the city of Norfolk.

    The state has been looking at designs for the past 20 years to improve traffic flow in the area, according to a report in the Virginian-Pilot newspaper. Hampton Roads is a body of water making up one of the world's largest natural harbours. The existing structure is close to the US Navy's Atlantic Fleet home base at Norfolk.