SSL settles legal issues, Champlain Bridge to open December 21

Montreal will get its new Champlain Bridge just before Christmas, a date agreed upon by the Canadian government and the SNC-Lavalin-led consortium. The agreement settles an outstanding lawsuit that the Consortium had filed regarding costs increases of around US$186.5 million relating to the transportation of oversized parts and delays to the bridge's construction, according to media reports. Last month SNC-Lavalin, head of the Signature on the Saint-Laurent Group (SSL), had said that the bridge over the
April 18, 2018 Read time: 2 mins
Merry Christmas to Montreal: Champlain Bridge replacement opens in December

Montreal will get its new Champlain Bridge just before Christmas, a date agreed upon by the Canadian government and the SNC-Lavalin-led consortium.

The agreement settles an outstanding lawsuit that the Consortium had filed regarding costs increases of around US$186.5 million relating to the transportation of oversized parts and delays to the bridge's construction, according to media reports.

Last month SNC-Lavalin, head of the Signature on the Saint-Laurent Group (SSL), had said that the bridge over the St Lawrence River and Seaway canal would open in December but gave no date. The December 21 date it newly three weeks later than planned.

Failure to open the 3.4km-long bridge to vehicular traffic on time means the consortium would face stiff fines, according to media reports: around $77,500 a day for the first seven days followed by $310,000 per day.

No details of the settlement were released.

Cost of the entire 6km corridor project is set at US$3.3 billion of which around $1.8 billion is for construction of the bridge, approach roads and highway adjustments.

The federal Canadian government signed a public-private partnership deal with the SNC-Lavalin consortium Signature on the Saint-Laurent Group in mid-2015 for the group to design, build, finance and maintain the New Champlain Bridge Corridor project. SNC-Lavalin is a 50% partner in SSL which will operate and maintain the bridge until October 2049. Other SSL partners are Hochtief, Flatiron, Dragados Canada and Grupo ACS.

Meanwhile, SSL entered into a date-certain, fixed-priced contract with a construction joint venture of which SNC-Lavalin is again a 50% partner.

The new bridge has six vehicle lanes plus two lanes running in the middle of the bridge for electric public transit trains. The bridge runs from the Ile des Soeurs to Brossard, immediately downstream from the existing Champlain Bridge.

Every year, around 50 million vehicles cross the old bridge, Canada’s most heavily travelled bridge and a major route for traffic to and from the US. Construction of the existing steel truss cantilever bridge, as well as accompanying approaches and the Bonaventure Expressway, started in 1957 and finished in 1962. Of the old 14.5km-long complex, the bridge is 7.4km.

Related Content

  • India plans major infrastucture investment
    February 10, 2012
    India says it turned its Commonwealth Games into a world-class success, and now it aims to do the same with its infrastructure. Patrick Smith reports. On October, 2010 India put itself on the world stage, and disaster appeared to loom as a catalogue of problems dogged its biggest ever sporting event. Costing nearly US$2 billion to stage, the most expensive Commonwealth Games ever were, according to some, in doubt.
  • India plans major infrastucture investment
    April 5, 2012
    India says it turned its Commonwealth Games into a world-class success, and now it aims to do the same with its infrastructure. Patrick Smith reports On October, 2010 India put itself on the world stage, and disaster appeared to loom as a catalogue of problems dogged its biggest ever sporting event. Costing nearly US$2 billion to stage, the most expensive Commonwealth Games ever were, according to some, in doubt. After years of planning some projects were incomplete, there were health scares and a br
  • Athabasca’s Hwy 813 bridge to be replaced
    May 16, 2022
    The new bridge over the Athabasca River in the Canadian province of Alberta will include two 3.7m-wide lanes with 1.8m-wide shoulders on either side as well as a pedestrian sidewalk.
  • Florida highway rebuild project
    May 2, 2018
    Rebuilding a congested stretch of highway in Florida will cut congestion and boost safety for commuters - Mike Woof writes. Florida’s 214km-long I-4 highway provides a key transport route between Tampa and Daytona Beach, but has an unenviable reputation for both congestion and safety, with frequent delays due to heavy traffic as well as crashes. The stretch running through the city of Orlando is particularly prone to jams at peak periods, with huge traffic volumes resulting in vehicles having to slow to a c