SSL settles legal issues, Champlain Bridge to open December 21

Montreal will get its new Champlain Bridge just before Christmas, a date agreed upon by the Canadian government and the SNC-Lavalin-led consortium. The agreement settles an outstanding lawsuit that the Consortium had filed regarding costs increases of around US$186.5 million relating to the transportation of oversized parts and delays to the bridge's construction, according to media reports. Last month SNC-Lavalin, head of the Signature on the Saint-Laurent Group (SSL), had said that the bridge over the
April 18, 2018 Read time: 2 mins
Merry Christmas to Montreal: Champlain Bridge replacement opens in December

Montreal will get its new Champlain Bridge just before Christmas, a date agreed upon by the Canadian government and the SNC-Lavalin-led consortium.

The agreement settles an outstanding lawsuit that the Consortium had filed regarding costs increases of around US$186.5 million relating to the transportation of oversized parts and delays to the bridge's construction, according to media reports.

Last month SNC-Lavalin, head of the Signature on the Saint-Laurent Group (SSL), had said that the bridge over the St Lawrence River and Seaway canal would open in December but gave no date. The December 21 date it newly three weeks later than planned.

Failure to open the 3.4km-long bridge to vehicular traffic on time means the consortium would face stiff fines, according to media reports: around $77,500 a day for the first seven days followed by $310,000 per day.

No details of the settlement were released.

Cost of the entire 6km corridor project is set at US$3.3 billion of which around $1.8 billion is for construction of the bridge, approach roads and highway adjustments.

The federal Canadian government signed a public-private partnership deal with the SNC-Lavalin consortium Signature on the Saint-Laurent Group in mid-2015 for the group to design, build, finance and maintain the New Champlain Bridge Corridor project. SNC-Lavalin is a 50% partner in SSL which will operate and maintain the bridge until October 2049. Other SSL partners are Hochtief, Flatiron, Dragados Canada and Grupo ACS.

Meanwhile, SSL entered into a date-certain, fixed-priced contract with a construction joint venture of which SNC-Lavalin is again a 50% partner.

The new bridge has six vehicle lanes plus two lanes running in the middle of the bridge for electric public transit trains. The bridge runs from the Ile des Soeurs to Brossard, immediately downstream from the existing Champlain Bridge.

Every year, around 50 million vehicles cross the old bridge, Canada’s most heavily travelled bridge and a major route for traffic to and from the US. Construction of the existing steel truss cantilever bridge, as well as accompanying approaches and the Bonaventure Expressway, started in 1957 and finished in 1962. Of the old 14.5km-long complex, the bridge is 7.4km.

Related Content

  • Virginia Interstate highway upgrade project
    February 26, 2019
    A 15km stretch of Interstate 64 in the US state of Virginia will be upgraded, allowing it to handle more traffic.
  • Private owners seek a buyer for the UK’s only toll road, M6 Toll
    February 15, 2016
    Britain’s only toll road, the motorway M6 Toll, is up for sale by its owners, a consortium of banks that hope to recover some of the €2.45 billion of debt. The 27 owners of M6 Toll, including Crédit Agricole, Commerzbank and Banco Espirito Santo, took over the 43km pay-as-you-go toll road from infrastructure group Macquarie in December 2013 after a debt restructuring. Midland Expressway Limited (MEL), part of Macquarie Atlas Roads, continues to operate the six-lane motorway around the English city of
  • Official sale of M6 Toll to be launched in September
    August 23, 2016
    An information memorandum that will officially launch the sale of M6 Toll, the UK’s only toll road, will be sent out to interested buyers in September. No date is set for sending out the IM, according to sources, but the 43km six-lane asset around the English city of Birmingham could be going for slightly less after the UK’s European Union referendum vote in June. The result of the so-called Brexit – ‘British exit’ of the EU – referendum was won by the no-to-Europe side and the UK is now setting up t
  • Safety issues fuel interest at PIARC’s tunnel conference in Lyon
    June 4, 2019
    Alternative fuel and automated vehicle issues occupied minds at PIARC’s first international road tunnel safety conference. David Arminas reports from Lyon More than ever, tunnel management must done in a wholistic fashion, said Andre Broto, president of PIARC, the World Road Association, based in Paris. With those sentiments, Broto kicked off PIARC’s first International Conference on Tunnel Operations and Safety. One of the first speakers, Sandrine Bernabei Chinzi, head of transport infrastructure at Fr