SSL settles legal issues, Champlain Bridge to open December 21

Montreal will get its new Champlain Bridge just before Christmas, a date agreed upon by the Canadian government and the SNC-Lavalin-led consortium. The agreement settles an outstanding lawsuit that the Consortium had filed regarding costs increases of around US$186.5 million relating to the transportation of oversized parts and delays to the bridge's construction, according to media reports. Last month SNC-Lavalin, head of the Signature on the Saint-Laurent Group (SSL), had said that the bridge over the
April 18, 2018 Read time: 2 mins
Merry Christmas to Montreal: Champlain Bridge replacement opens in December

Montreal will get its new Champlain Bridge just before Christmas, a date agreed upon by the Canadian government and the SNC-Lavalin-led consortium.

The agreement settles an outstanding lawsuit that the Consortium had filed regarding costs increases of around US$186.5 million relating to the transportation of oversized parts and delays to the bridge's construction, according to media reports.

Last month SNC-Lavalin, head of the Signature on the Saint-Laurent Group (SSL), had said that the bridge over the St Lawrence River and Seaway canal would open in December but gave no date. The December 21 date it newly three weeks later than planned.

Failure to open the 3.4km-long bridge to vehicular traffic on time means the consortium would face stiff fines, according to media reports: around $77,500 a day for the first seven days followed by $310,000 per day.

No details of the settlement were released.

Cost of the entire 6km corridor project is set at US$3.3 billion of which around $1.8 billion is for construction of the bridge, approach roads and highway adjustments.

The federal Canadian government signed a public-private partnership deal with the SNC-Lavalin consortium Signature on the Saint-Laurent Group in mid-2015 for the group to design, build, finance and maintain the New Champlain Bridge Corridor project. SNC-Lavalin is a 50% partner in SSL which will operate and maintain the bridge until October 2049. Other SSL partners are Hochtief, Flatiron, Dragados Canada and Grupo ACS.

Meanwhile, SSL entered into a date-certain, fixed-priced contract with a construction joint venture of which SNC-Lavalin is again a 50% partner.

The new bridge has six vehicle lanes plus two lanes running in the middle of the bridge for electric public transit trains. The bridge runs from the Ile des Soeurs to Brossard, immediately downstream from the existing Champlain Bridge.

Every year, around 50 million vehicles cross the old bridge, Canada’s most heavily travelled bridge and a major route for traffic to and from the US. Construction of the existing steel truss cantilever bridge, as well as accompanying approaches and the Bonaventure Expressway, started in 1957 and finished in 1962. Of the old 14.5km-long complex, the bridge is 7.4km.

Related Content

  • VIDEO: Pittsburgh says goodbye to 108-year-old Hulton Bridge
    January 27, 2016
    It took 500 explosive charges to bring down a 108-year-old truss bridge in the US city of Pittsburgh and crews had three days to clear up the debris, according to local news stations.

    The blasts dropped the spans of 407m-long Jonathon Hulton Bridge directly into the Allegheny River. It was the first major bridge designed by Allegheny County in the state of Pennsylvania and connected the eastern Pittsburgh city suburbs of Oakmont and Harmarville.
  • Systra, Kiewit and Hatch to build third bridge in Kingston, Canada
    August 31, 2018
    Kingston, Canada, has selected Systra International Bridge Technologies, Peter Kiewit Sons and Hatch as the preferred consortium for the design and build Third Crossing project. Seven international teams answered the requests for proposals in February and 2018 with Systra, Kiewit and Hatch eventually chosen from a shortlist of three groups. The consortium will use an integrated project delivery model for the two-lane 1.2km bridge with a pedestrian and cycle path over the Cataraqui River will connect
  • $2.5bn plus investment in Canadian highway projects
    April 4, 2012
    Contracts worth a combined value of more than US$2.5billion have been awarded for two major Canadian highway construction projects. Spanish building firm, ACS, has been awarded a US$1.52billion contract to construct a new 27km eight-lane motorway. The contract also includes the operating of the road for 30 years. Meanwhile another Spanish construction firm, Ferrovial, working in association with SNC Lavalin, has been awarded the around US$1billion contract for the 20km extension of the Toronto 407 motorway
  • Bidding is healthy for a contract for the I-77 Interstate highway in the US state of North Carolina with Spanish firms competing
    April 4, 2012
    Bidding is healthy for the I-77 Interstate highway project in the US state of North Carolina. This 47km highway runs from the city of Charlotte to Mooresville and the contract will be for a 50 year period. Spanish construction companies ACS, OHL and Ferrovial are all amongst the bidder for the US$501.5 million package, which includes construction, maintenance and. French firm Vinci has formed a partnership with US companies Parsons, Archer Western and Blythe Construction. ACS has ACS formed a consortium wit