SSL settles legal issues, Champlain Bridge to open December 21

Montreal will get its new Champlain Bridge just before Christmas, a date agreed upon by the Canadian government and the SNC-Lavalin-led consortium. The agreement settles an outstanding lawsuit that the Consortium had filed regarding costs increases of around US$186.5 million relating to the transportation of oversized parts and delays to the bridge's construction, according to media reports. Last month SNC-Lavalin, head of the Signature on the Saint-Laurent Group (SSL), had said that the bridge over the
April 18, 2018 Read time: 2 mins
Merry Christmas to Montreal: Champlain Bridge replacement opens in December

Montreal will get its new Champlain Bridge just before Christmas, a date agreed upon by the Canadian government and the SNC-Lavalin-led consortium.

The agreement settles an outstanding lawsuit that the Consortium had filed regarding costs increases of around US$186.5 million relating to the transportation of oversized parts and delays to the bridge's construction, according to media reports.

Last month SNC-Lavalin, head of the Signature on the Saint-Laurent Group (SSL), had said that the bridge over the St Lawrence River and Seaway canal would open in December but gave no date. The December 21 date it newly three weeks later than planned.

Failure to open the 3.4km-long bridge to vehicular traffic on time means the consortium would face stiff fines, according to media reports: around $77,500 a day for the first seven days followed by $310,000 per day.

No details of the settlement were released.

Cost of the entire 6km corridor project is set at US$3.3 billion of which around $1.8 billion is for construction of the bridge, approach roads and highway adjustments.

The federal Canadian government signed a public-private partnership deal with the SNC-Lavalin consortium Signature on the Saint-Laurent Group in mid-2015 for the group to design, build, finance and maintain the New Champlain Bridge Corridor project. SNC-Lavalin is a 50% partner in SSL which will operate and maintain the bridge until October 2049. Other SSL partners are Hochtief, Flatiron, Dragados Canada and Grupo ACS.

Meanwhile, SSL entered into a date-certain, fixed-priced contract with a construction joint venture of which SNC-Lavalin is again a 50% partner.

The new bridge has six vehicle lanes plus two lanes running in the middle of the bridge for electric public transit trains. The bridge runs from the Ile des Soeurs to Brossard, immediately downstream from the existing Champlain Bridge.

Every year, around 50 million vehicles cross the old bridge, Canada’s most heavily travelled bridge and a major route for traffic to and from the US. Construction of the existing steel truss cantilever bridge, as well as accompanying approaches and the Bonaventure Expressway, started in 1957 and finished in 1962. Of the old 14.5km-long complex, the bridge is 7.4km.

Related Content

  • Taking the coast road on Reunion Island
    April 4, 2017
    An ambitious project on Reunion Island will improve transport
  • Controversial Russian bridge opens
    August 10, 2018
    The first stage of a controversial Russian bridge project is now complete, with the link having been opened to use by cars and buses. The Kerch Strait bridge spans the Black Sea, connecting Russia’s Taman Peninsula in Krasnodar with Crimea, the latter having been controversially annexed by Russia from Ukraine in 2014. The official opening of the 19km-long bridge was carried out by Russia’s president, Vladimir Putin, who drove across the link in a Russian-manufactured Kamaz truck to reach the city of Kerch.
  • Rader Hochbrücke construction set for summer
    April 7, 2025
    Work on the Rader Hochbrücke (bridge) near Rendsburg, Germany, will start this summer and take five years, according to DEGES.
  • Fierce competition for Toronto 407 ETR highway expansion contract
    April 24, 2014
    ACS of Spain and Ferrovial are competing for the contract to construct and exploit the second phase of expanding the 407 ETR highway in Toronto, Canada – one of the world’s biggest toll highways. Ferrovial has been managing the 407 ETR highway since 1999 and secured the first phase of its expansion. Currently, ACS and Ferrovial lead two of the three groups invited to present bids for the second phase of the expansion. The third group is headed by Canada's SNC Lavalin, which is Ferrovial's current partner i