SSL settles legal issues, Champlain Bridge to open December 21

Montreal will get its new Champlain Bridge just before Christmas, a date agreed upon by the Canadian government and the SNC-Lavalin-led consortium. The agreement settles an outstanding lawsuit that the Consortium had filed regarding costs increases of around US$186.5 million relating to the transportation of oversized parts and delays to the bridge's construction, according to media reports. Last month SNC-Lavalin, head of the Signature on the Saint-Laurent Group (SSL), had said that the bridge over the
April 18, 2018 Read time: 2 mins
Merry Christmas to Montreal: Champlain Bridge replacement opens in December

Montreal will get its new Champlain Bridge just before Christmas, a date agreed upon by the Canadian government and the SNC-Lavalin-led consortium.

The agreement settles an outstanding lawsuit that the Consortium had filed regarding costs increases of around US$186.5 million relating to the transportation of oversized parts and delays to the bridge's construction, according to media reports.

Last month SNC-Lavalin, head of the Signature on the Saint-Laurent Group (SSL), had said that the bridge over the St Lawrence River and Seaway canal would open in December but gave no date. The December 21 date it newly three weeks later than planned.

Failure to open the 3.4km-long bridge to vehicular traffic on time means the consortium would face stiff fines, according to media reports: around $77,500 a day for the first seven days followed by $310,000 per day.

No details of the settlement were released.

Cost of the entire 6km corridor project is set at US$3.3 billion of which around $1.8 billion is for construction of the bridge, approach roads and highway adjustments.

The federal Canadian government signed a public-private partnership deal with the SNC-Lavalin consortium Signature on the Saint-Laurent Group in mid-2015 for the group to design, build, finance and maintain the New Champlain Bridge Corridor project. SNC-Lavalin is a 50% partner in SSL which will operate and maintain the bridge until October 2049. Other SSL partners are Hochtief, Flatiron, Dragados Canada and Grupo ACS.

Meanwhile, SSL entered into a date-certain, fixed-priced contract with a construction joint venture of which SNC-Lavalin is again a 50% partner.

The new bridge has six vehicle lanes plus two lanes running in the middle of the bridge for electric public transit trains. The bridge runs from the Ile des Soeurs to Brossard, immediately downstream from the existing Champlain Bridge.

Every year, around 50 million vehicles cross the old bridge, Canada’s most heavily travelled bridge and a major route for traffic to and from the US. Construction of the existing steel truss cantilever bridge, as well as accompanying approaches and the Bonaventure Expressway, started in 1957 and finished in 1962. Of the old 14.5km-long complex, the bridge is 7.4km.

Related Content

  • Bulgaria lets contract for Struma Motorway’s Zheleznitsa Tunnel
    February 15, 2019
    A consortium including local firms GP Group, Global Construction and Via Plan will build the 2km Zheleznitsa Tunnel, part of the Struma Motorway. The contract is worth around €97.5 million and the tunnel will be the longest in Bulgaria. The EU Cohesion Fund will co-finance the project, along with the Bulgarian government under the Operational Programme Transport and Transport Infrastructure 2014-2020. Completion is set for the end of 2023. Two previous tender processes to award the construction con
  • Let’s Boogie in a new tunnel
    July 7, 2020
    The new Victory Boogie Woogie Tunnel will be the most sustainable tunnel in the Netherlands.
  • Make the case for electronic tolling, ASECAP conference delegates heard
    September 14, 2015
    Mobility pricing and electronic tolling is the future, delegates to a recent ASECAP Study Days conference, reports Geoff Hadwick at the Lisbon event. The international road tolling industry is failing to make its case and the sector is losing out to other social and political lobby groups. As a result, “tolling is still on the sidelines”, according to the head of the Washington-based International Bridge, Tunnel and Turnpike Association. IBTTA chief executive Pat Jones issued his stark warning at the
  • The US FAST Act: a job left unfinished
    April 4, 2016
    US roads and bridges are crumbling at an alarming rate as state governments wring their hands over the increasingly scarce money for repairs. Enter the FAST Act. But is it enough? US state transportation department officials, as well as highway contractors and operators, breathed a sigh of relief in December. For months the highways infrastructure sector waited anxiously to see where the necessary money for road projects would come from. For several years, the Highways Trust Fund – the usual way of paying f