SSL settles legal issues, Champlain Bridge to open December 21

Montreal will get its new Champlain Bridge just before Christmas, a date agreed upon by the Canadian government and the SNC-Lavalin-led consortium. The agreement settles an outstanding lawsuit that the Consortium had filed regarding costs increases of around US$186.5 million relating to the transportation of oversized parts and delays to the bridge's construction, according to media reports. Last month SNC-Lavalin, head of the Signature on the Saint-Laurent Group (SSL), had said that the bridge over the
April 18, 2018 Read time: 2 mins
Merry Christmas to Montreal: Champlain Bridge replacement opens in December

Montreal will get its new Champlain Bridge just before Christmas, a date agreed upon by the Canadian government and the SNC-Lavalin-led consortium.

The agreement settles an outstanding lawsuit that the Consortium had filed regarding costs increases of around US$186.5 million relating to the transportation of oversized parts and delays to the bridge's construction, according to media reports.

Last month SNC-Lavalin, head of the Signature on the Saint-Laurent Group (SSL), had said that the bridge over the St Lawrence River and Seaway canal would open in December but gave no date. The December 21 date it newly three weeks later than planned.

Failure to open the 3.4km-long bridge to vehicular traffic on time means the consortium would face stiff fines, according to media reports: around $77,500 a day for the first seven days followed by $310,000 per day.

No details of the settlement were released.

Cost of the entire 6km corridor project is set at US$3.3 billion of which around $1.8 billion is for construction of the bridge, approach roads and highway adjustments.

The federal Canadian government signed a public-private partnership deal with the SNC-Lavalin consortium Signature on the Saint-Laurent Group in mid-2015 for the group to design, build, finance and maintain the New Champlain Bridge Corridor project. SNC-Lavalin is a 50% partner in SSL which will operate and maintain the bridge until October 2049. Other SSL partners are Hochtief, Flatiron, Dragados Canada and Grupo ACS.

Meanwhile, SSL entered into a date-certain, fixed-priced contract with a construction joint venture of which SNC-Lavalin is again a 50% partner.

The new bridge has six vehicle lanes plus two lanes running in the middle of the bridge for electric public transit trains. The bridge runs from the Ile des Soeurs to Brossard, immediately downstream from the existing Champlain Bridge.

Every year, around 50 million vehicles cross the old bridge, Canada’s most heavily travelled bridge and a major route for traffic to and from the US. Construction of the existing steel truss cantilever bridge, as well as accompanying approaches and the Bonaventure Expressway, started in 1957 and finished in 1962. Of the old 14.5km-long complex, the bridge is 7.4km.

Related Content

  • Thailand highway bidding process opening
    October 12, 2017
    Tenders for two expressway projects in Thailand will open by mid-2018. The projects are worth around US$1.5 billion in all. The tender process is being handled by the Expressway Authority of Thailand (Exat). Construction of one of the expressways should commence by late 2018 and the route would then be open to traffic by the end of 2021, if all goes to plan. The 10.5km expressway will connect the N2 Nawamin Road with the Kasetsart intersection and will be tolled, with a project traffic volume of 80,000
  • New Cape Fear Memorial Bridge may be a toll
    June 2, 2025
    Councillors leave option open for charges on proposed new river crossing
  • New ring road to solve problem of traffic jams in Ukraine capital Kiev
    May 10, 2018
    Ukraine’s capital Kiev will benefit from a new ring road – Eugene Gerden writes The government of Ukraine, together with the authorities of the Ukrainian capital Kiev, plans to invest up to US$2 billion in the building of a new ring road around the city. The new road, known as the Great Ring Road, will be around 200km long, of which 65km will be of existing roads and 148km of new roads. The ring road will connect three international transport corridors that run through the territory of Ukraine, as well
  • Serbia tunnel link bored for Corridor 10 project
    August 7, 2017
    Work is underway for two key tunnel sections on Serbia’s section of the Corridor 10 project, which forms the country’s stretch of the E-75 highway route. The 1.8km Manajle Tunnel is the longest of several to be built for the Corridor 10 project and features twin tubes that run between 30 and 35m apart. The Predajane Tunnel is 1.1km long, again with twin tubes and in its case, these run from 35-65m apart. A Bulgarian contractor, Consortium Alliance X, is building the Manajle Tunnel, with the work valued at a