SSL settles legal issues, Champlain Bridge to open December 21

Montreal will get its new Champlain Bridge just before Christmas, a date agreed upon by the Canadian government and the SNC-Lavalin-led consortium. The agreement settles an outstanding lawsuit that the Consortium had filed regarding costs increases of around US$186.5 million relating to the transportation of oversized parts and delays to the bridge's construction, according to media reports. Last month SNC-Lavalin, head of the Signature on the Saint-Laurent Group (SSL), had said that the bridge over the
April 18, 2018 Read time: 2 mins
Merry Christmas to Montreal: Champlain Bridge replacement opens in December

Montreal will get its new Champlain Bridge just before Christmas, a date agreed upon by the Canadian government and the SNC-Lavalin-led consortium.

The agreement settles an outstanding lawsuit that the Consortium had filed regarding costs increases of around US$186.5 million relating to the transportation of oversized parts and delays to the bridge's construction, according to media reports.

Last month SNC-Lavalin, head of the Signature on the Saint-Laurent Group (SSL), had said that the bridge over the St Lawrence River and Seaway canal would open in December but gave no date. The December 21 date it newly three weeks later than planned.

Failure to open the 3.4km-long bridge to vehicular traffic on time means the consortium would face stiff fines, according to media reports: around $77,500 a day for the first seven days followed by $310,000 per day.

No details of the settlement were released.

Cost of the entire 6km corridor project is set at US$3.3 billion of which around $1.8 billion is for construction of the bridge, approach roads and highway adjustments.

The federal Canadian government signed a public-private partnership deal with the SNC-Lavalin consortium Signature on the Saint-Laurent Group in mid-2015 for the group to design, build, finance and maintain the New Champlain Bridge Corridor project. SNC-Lavalin is a 50% partner in SSL which will operate and maintain the bridge until October 2049. Other SSL partners are Hochtief, Flatiron, Dragados Canada and Grupo ACS.

Meanwhile, SSL entered into a date-certain, fixed-priced contract with a construction joint venture of which SNC-Lavalin is again a 50% partner.

The new bridge has six vehicle lanes plus two lanes running in the middle of the bridge for electric public transit trains. The bridge runs from the Ile des Soeurs to Brossard, immediately downstream from the existing Champlain Bridge.

Every year, around 50 million vehicles cross the old bridge, Canada’s most heavily travelled bridge and a major route for traffic to and from the US. Construction of the existing steel truss cantilever bridge, as well as accompanying approaches and the Bonaventure Expressway, started in 1957 and finished in 1962. Of the old 14.5km-long complex, the bridge is 7.4km.

Related Content

  • Weigh-in-motion key to maximising road life
    February 24, 2012
    The market and technology for weigh-in-motion systems continues to evolve – Mike Woof writes. for both mature and developing highway infrastructure networks, traffic densities play an important role in determining road wear and life. Monitoring traffic volumes and individual vehicle weight is crucial for ensuring roads can cope in the long term and that maintenance can be planned, while the problem of overloading can be eliminated.
  • Mostotrest won another tender for building of Moscow-St Petersburg highway
    February 20, 2014
    The award for a key stretch of the Moscow-St Petersburg highway has been awarded - Eugene Gerden writes As expected by analysts, Mostotrest, owned by the Rotenberg brothers, won the tender for the construction of the sixth and longest section of the Moscow-St Petersburg highway. Under the conditions of the tender the company will build 209km of the highway (334-543km), which will pass through the Tver and Novgorod regions of Russia. The cost of construction is 144.6 billion Rubles (US$4.51 billion), 16 bill
  • Britain’s M6toll rewards its 190 millionth customer
    May 18, 2016
    Britain’s M6toll motorway - now up for sale - has awarded its 190 millionth customer with a year’s free travel. James Hodson, director of motorway operations for toll road operator Midland Expressway, said it could save the driver around €2,550 over the year. The driver’s car was fitted with an M6toll Tag, a small electronic device fitted to a vehicle’s windscreen. It allows users to pre-pay for their journeys and pass through a dedicated lane usually without the need to stop. Tags normally cost a mon
  • Noise camera knowledge is far from sound
    February 7, 2025
    Despite the UK public wanting measures to tackle noisy vehicles, knowledge of noise cameras, such as the SoundVue system from Intelligent Instruments, is low, according to a recent poll.