SSL settles legal issues, Champlain Bridge to open December 21

Montreal will get its new Champlain Bridge just before Christmas, a date agreed upon by the Canadian government and the SNC-Lavalin-led consortium. The agreement settles an outstanding lawsuit that the Consortium had filed regarding costs increases of around US$186.5 million relating to the transportation of oversized parts and delays to the bridge's construction, according to media reports. Last month SNC-Lavalin, head of the Signature on the Saint-Laurent Group (SSL), had said that the bridge over the
April 18, 2018 Read time: 2 mins
Merry Christmas to Montreal: Champlain Bridge replacement opens in December

Montreal will get its new Champlain Bridge just before Christmas, a date agreed upon by the Canadian government and the SNC-Lavalin-led consortium.

The agreement settles an outstanding lawsuit that the Consortium had filed regarding costs increases of around US$186.5 million relating to the transportation of oversized parts and delays to the bridge's construction, according to media reports.

Last month SNC-Lavalin, head of the Signature on the Saint-Laurent Group (SSL), had said that the bridge over the St Lawrence River and Seaway canal would open in December but gave no date. The December 21 date it newly three weeks later than planned.

Failure to open the 3.4km-long bridge to vehicular traffic on time means the consortium would face stiff fines, according to media reports: around $77,500 a day for the first seven days followed by $310,000 per day.

No details of the settlement were released.

Cost of the entire 6km corridor project is set at US$3.3 billion of which around $1.8 billion is for construction of the bridge, approach roads and highway adjustments.

The federal Canadian government signed a public-private partnership deal with the SNC-Lavalin consortium Signature on the Saint-Laurent Group in mid-2015 for the group to design, build, finance and maintain the New Champlain Bridge Corridor project. SNC-Lavalin is a 50% partner in SSL which will operate and maintain the bridge until October 2049. Other SSL partners are Hochtief, Flatiron, Dragados Canada and Grupo ACS.

Meanwhile, SSL entered into a date-certain, fixed-priced contract with a construction joint venture of which SNC-Lavalin is again a 50% partner.

The new bridge has six vehicle lanes plus two lanes running in the middle of the bridge for electric public transit trains. The bridge runs from the Ile des Soeurs to Brossard, immediately downstream from the existing Champlain Bridge.

Every year, around 50 million vehicles cross the old bridge, Canada’s most heavily travelled bridge and a major route for traffic to and from the US. Construction of the existing steel truss cantilever bridge, as well as accompanying approaches and the Bonaventure Expressway, started in 1957 and finished in 1962. Of the old 14.5km-long complex, the bridge is 7.4km.

Related Content

  • Work to start on triple-deck roundabout in North Tyneside, UK
    June 30, 2016
    Construction of a major triple-deck roundabout in North Tyneside, England starts in August.

    The roundabout is part of an upgrade to the A19/A1058 Coast Road junction that includes lowering the A19 beneath the existing A1058 Coast Road and roundabout.

    The €90 million scheme is on the main route to and from the Tyne Tunnel and will mean that people travelling along the A19 will no longer have to queue at the roundabout to go continue their journey straight ahead. Instead, drivers will use a new section of road which will run under the junction.
  • Highway developments to boost east-west transport
    February 16, 2012
    Huge highway developments are being planned and carried out to further improve East-West transport, with Central Asia a key region as Patrick Smith reports
  • Bentley announces finalists for the 2017 Be Inspired Awards
    August 11, 2017
    AECOM, Arcadis-WSP/PB, CH2M-Fairhurst and Highways England are among the finalists for this year’s Bentley awards for outstanding use of BIM – building information modelling. Bentley Systems, a provider of infrastructure software solutions, said that the winners will be announced at The Year in Infrastructure 2017 Conference to be held in Singapore this year, October 10-12. “The annual awards honour the extraordinary work of Bentley users advancing infrastructure design, construction, and operations through
  • Mersey Gateway: Consortia Talks
    April 4, 2012
    The competitive dialogue phase of the Mersey Gateway Project has begun. The project team are said to have held initial meetings with the three shortlisted bidding consortia, and will be working closely with each of them over the coming months. The aim is for each of the three bidders to submit their detailed proposals by the end of 2012, with an announcement about a preferred bidder likely to come in spring 2013. The value of the construction phase of the project, including land, is estimated at US$961milli