SSL settles legal issues, Champlain Bridge to open December 21

Montreal will get its new Champlain Bridge just before Christmas, a date agreed upon by the Canadian government and the SNC-Lavalin-led consortium. The agreement settles an outstanding lawsuit that the Consortium had filed regarding costs increases of around US$186.5 million relating to the transportation of oversized parts and delays to the bridge's construction, according to media reports. Last month SNC-Lavalin, head of the Signature on the Saint-Laurent Group (SSL), had said that the bridge over the
April 18, 2018 Read time: 2 mins
Merry Christmas to Montreal: Champlain Bridge replacement opens in December

Montreal will get its new Champlain Bridge just before Christmas, a date agreed upon by the Canadian government and the SNC-Lavalin-led consortium.

The agreement settles an outstanding lawsuit that the Consortium had filed regarding costs increases of around US$186.5 million relating to the transportation of oversized parts and delays to the bridge's construction, according to media reports.

Last month SNC-Lavalin, head of the Signature on the Saint-Laurent Group (SSL), had said that the bridge over the St Lawrence River and Seaway canal would open in December but gave no date. The December 21 date it newly three weeks later than planned.

Failure to open the 3.4km-long bridge to vehicular traffic on time means the consortium would face stiff fines, according to media reports: around $77,500 a day for the first seven days followed by $310,000 per day.

No details of the settlement were released.

Cost of the entire 6km corridor project is set at US$3.3 billion of which around $1.8 billion is for construction of the bridge, approach roads and highway adjustments.

The federal Canadian government signed a public-private partnership deal with the SNC-Lavalin consortium Signature on the Saint-Laurent Group in mid-2015 for the group to design, build, finance and maintain the New Champlain Bridge Corridor project. SNC-Lavalin is a 50% partner in SSL which will operate and maintain the bridge until October 2049. Other SSL partners are Hochtief, Flatiron, Dragados Canada and Grupo ACS.

Meanwhile, SSL entered into a date-certain, fixed-priced contract with a construction joint venture of which SNC-Lavalin is again a 50% partner.

The new bridge has six vehicle lanes plus two lanes running in the middle of the bridge for electric public transit trains. The bridge runs from the Ile des Soeurs to Brossard, immediately downstream from the existing Champlain Bridge.

Every year, around 50 million vehicles cross the old bridge, Canada’s most heavily travelled bridge and a major route for traffic to and from the US. Construction of the existing steel truss cantilever bridge, as well as accompanying approaches and the Bonaventure Expressway, started in 1957 and finished in 1962. Of the old 14.5km-long complex, the bridge is 7.4km.

Related Content

  • Economic gains from widening the A453 in Nottingham, England
    August 12, 2014
    Work is well underway on turning a busy just over 11km two-lane link road from the city of Nottingham to Junction 24 of the M1 in Leicestershire, England into a four-lane highway. The widened highway will relieve considerable peak-time congestion for travellers to Nottingham, the M1 and East Midlands Airport while also making journeys safer and more reliable. Guy Woodford reports Used by up to 30,000 vehicles a day, the A453 is renowned for congestion at peak travel times. But years of day-to-day commuter a
  • Dubai infrastructure development
    March 24, 2017
    New infrastructure is being built in Dubai with the help of machines from Volvo CE The Dubai Water Canal is being built in a busy and congested urban area, with the project including construction of major new road bridge crossings. The work is being carried out by Turkish infrastructure specialist DETECH Contracting. The 3.2km waterway is being built through downtown Dubai and is among the most ambitious projects being carried out in the country. When fully opened in 2017 the project – called The Duba
  • Major highway widening project in Netherlands
    December 15, 2014
    A major highway widening and upgrade project is being carried out in the Netherlands in a bid to improve traffic flow on some of Europe’s busiest routes. SAAone is carrying out the work for the A1-A6 motorway project for Rijkswaterstaat, the Dutch Directorate-General for Public Works and Water Management. A key component of the project is adding new lanes to the A1 and A6 highways.
  • Major Australian tunnel contract has been awarded
    October 29, 2021
    A major Australian tunnel contract has been awarded to a consortium.