SSL settles legal issues, Champlain Bridge to open December 21

Montreal will get its new Champlain Bridge just before Christmas, a date agreed upon by the Canadian government and the SNC-Lavalin-led consortium. The agreement settles an outstanding lawsuit that the Consortium had filed regarding costs increases of around US$186.5 million relating to the transportation of oversized parts and delays to the bridge's construction, according to media reports. Last month SNC-Lavalin, head of the Signature on the Saint-Laurent Group (SSL), had said that the bridge over the
April 18, 2018 Read time: 2 mins
Merry Christmas to Montreal: Champlain Bridge replacement opens in December

Montreal will get its new Champlain Bridge just before Christmas, a date agreed upon by the Canadian government and the SNC-Lavalin-led consortium.

The agreement settles an outstanding lawsuit that the Consortium had filed regarding costs increases of around US$186.5 million relating to the transportation of oversized parts and delays to the bridge's construction, according to media reports.

Last month SNC-Lavalin, head of the Signature on the Saint-Laurent Group (SSL), had said that the bridge over the St Lawrence River and Seaway canal would open in December but gave no date. The December 21 date it newly three weeks later than planned.

Failure to open the 3.4km-long bridge to vehicular traffic on time means the consortium would face stiff fines, according to media reports: around $77,500 a day for the first seven days followed by $310,000 per day.

No details of the settlement were released.

Cost of the entire 6km corridor project is set at US$3.3 billion of which around $1.8 billion is for construction of the bridge, approach roads and highway adjustments.

The federal Canadian government signed a public-private partnership deal with the SNC-Lavalin consortium Signature on the Saint-Laurent Group in mid-2015 for the group to design, build, finance and maintain the New Champlain Bridge Corridor project. SNC-Lavalin is a 50% partner in SSL which will operate and maintain the bridge until October 2049. Other SSL partners are Hochtief, Flatiron, Dragados Canada and Grupo ACS.

Meanwhile, SSL entered into a date-certain, fixed-priced contract with a construction joint venture of which SNC-Lavalin is again a 50% partner.

The new bridge has six vehicle lanes plus two lanes running in the middle of the bridge for electric public transit trains. The bridge runs from the Ile des Soeurs to Brossard, immediately downstream from the existing Champlain Bridge.

Every year, around 50 million vehicles cross the old bridge, Canada’s most heavily travelled bridge and a major route for traffic to and from the US. Construction of the existing steel truss cantilever bridge, as well as accompanying approaches and the Bonaventure Expressway, started in 1957 and finished in 1962. Of the old 14.5km-long complex, the bridge is 7.4km.

Related Content

  • Boom in Asian infrastructure investment
    April 5, 2012
    Investment in China and India continues unabated, but other nations on the continent are eager to attract companies as Patrick Smith reports Asia is still booming despite the current economic crisis, and new infrastructure programmes are constantly coming on stream. Powerhouses China and India, with their double-digit growth figures and huge infrastructure plans (in scope and cost), are leading the way and are still magnets for businesses wishing to expand, both in terms of facilities and customers. But oth
  • Colombia dual carriageways under construction
    October 10, 2016
    Colombia is currently working on major highway projects that will improve transport infrastructure in the country and form part of its 4G programme. The US$616.5 million Rumichaca-Pasto dual carriageway in Narino department will improve Colombia’s transport connections with neighbouring Ecuador, cutting journey times from two hours at present to just one hour. The project is being handled by a consortium, Consorcio SAC 4G and involves improving an 80km road section and building additional lanes for the 74km
  • Busy bridge in Beijing replaced quickly
    March 31, 2016
    The replacement of a very busy road bridge in China’s capital Beijing has been carried out successfully. Due to the volume of traffic using the bridge during week days, the work had to be carried out quickly so as to minimise traffic disruption. But despite being carried out in the centre of Beijing, the replacement work for the Sanyuan Bridge just took 43 hours from start to completion.
  • Five consortia line up for Denmark’s new Storstrøm Bridge project
    June 18, 2015
    The Danish government has shortlisted five consortia for construction of a new Storstrøm Bridge to replace an aging structure. The cost of the bridge connecting the Danish islands of Zealand and Falstser amounts to nearly €563 million (US$625.7 million) and the bridge will be financed by the government's Infrastructure Fund. Companies that qualified for the project are a joint venture consisting of Vinci Construction Grand ProjectsSAS, Hochtief Infrastructure GmbH and MT Højgaard; the consortium of St