SSL hits back over criticism of its work on the Champlain Bridge

The contactor building the replacement Champlain Bridge in Canada has hit back over of allegations of poor workmanship in the US$3.3 billion project. The new 3.4km cable-stayed Champlain Bridge over the St Lawrence River will have six lanes vehicle lanes and a separate cycle and pedestrian lane. Design life is 125 years and is being constructed under a public-private partnership and operating contract of 30 years after completion of construction. Work includes construction of a smaller bridge for Île des
December 11, 2017 Read time: 3 mins
The 3.4km cable-stayed Champlain Bridge ill have six lanes vehicle lanes and a separate cycle and pedestrian lane (photo courtesy Infrastructure Canada).jpg

The contactor building the replacement Champlain Bridge in Canada has hit back over of allegations of poor workmanship in the US$3.3 billion project.

The new 3.4km cable-stayed Champlain Bridge over the St Lawrence River will have six lanes vehicle lanes and a separate cycle and pedestrian lane. Design life is 125 years and is being constructed under a public-private partnership and operating contract of 30 years after completion of construction.

Work includes construction of a smaller bridge for Île des Soeurs - Nun’s Island - and widening Autoroute 15 through the centre of Montreal.

Infrastructure Canada, an agency of the federal Canadian government, is the client. Construction started in June 2015 and the bridge is on target for opening in December next year, according to SSL. Annual traffic is estimated to be round 60 million vehicles because the bridge is part of a major route into the US.

Recent media reports have suggested the SSL has had problems with poor welding, misaligned holes on steel sections and cracked steel plates.

Daniel Genest, director of co-ordination for the project, said all material meets strict quality standards. Most of the material is being built in factories in the Quebec province cities of Trois-Rivières, Quebec City, Terrebonne and also in Madrid, Spain. Genest said every piece that arrives on site is thoroughly inspected by engineers working for subcontractors.

Further inspections are carried out by an independent engineer hired by Infrastructure Canada and SSL. Infrastructure Canada also does testing on some material in its own lab.

Genest acknowledged that inspection had found problem with some material but the vast majority were minor and easily corrected.

He said that there were around 3,000 reports of “non-conformity” to standards of which 2,500 were related to the bridge and the rest to a section of Autoroute 15. There were 82 parts identified as having major defects, Genest said.

“It’s normal in the sense that if you don’t have [non-conformity reports] in place, it means you don’t have a good quality-control system,” he said.

SSL includes: SNC-Lavalin, ACS Infrastructure, Dragados Canada, Flatiron Constructors Canada and EBC. TY Lin International is lead designer.

The old steel truss and cantilever Champlain Bridge opened in 1962 after five years of construction. Traffic on the six-lane 3.4km structure is around 160,000 vehicles a day. It was built by Atlas Construction, McNamara (Quebec), Key Construction, Deschamps & Bélanger and the Dominion Bridge Company.

In 2013, one lane was closed after a crack was discovered in the superstructure. During emergency repairs, the crack enlarged and a second lane was closed, forcing consideration of building a replacement bridge.

Related Content

  • How waste plastic and soybean oil are helping our roads last longer
    April 13, 2018
    A new super-modifier is born from waste plastic in Italy and a soybean-based rejuvenator from the US spreads from its home market. By Kristina Smith The two bitumen technologies featured this month come from almost opposing sources. One emerges from the human-created plastic waste plaguing our planet, the other from a plant. However, both technologies have been created with the same aims: to increase the life of roads, saving cost and ultimately reducing the impact of road building on the planet. A coll
  • New NY Bridge - Tappan Zee - main span towers poured
    December 16, 2016
    One of the largest US infrastructure projects is nearer completion after recent topping out of the eight main span towers of the New NY Bridge. The final concrete pour was in mid-December and all piles - more than 1,000 - have been installed in Hudson River. To date, 3,000 roadway panels for the approaches - making 5.5km in length - have been installed, according to the New York State Thruway Authority, owner of the New NY Bridge project. The New NY Bridge, also called the Tappan Zee Bridge, is on tra
  • IRF Geneva takes centre stage at Movin’ On event in Canada
    September 27, 2017
    The Challenge Bibendum organised by Michelin for the past 20 years had now become “Movin’On”. Organised in Canada on 13th-15the June 2017, in this new avatar and focus, the event had attracted 4,000 participants from the transportation industry from 31 countries around the world. IRF Geneva was represented by its executive director, Susanna Zammataro.
  • Strong investment growth in the world’s highways was a key driver in John Deere and Wirtgen coming together
    December 21, 2017
    John Deere’s recent acquisition of the Wirtgen Group was driven by the way in which two leading equipment manufacturers could come together with no product overlap and target strong investment growth in the world’s highways sector