SSL hits back over criticism of its work on the Champlain Bridge

The contactor building the replacement Champlain Bridge in Canada has hit back over of allegations of poor workmanship in the US$3.3 billion project. The new 3.4km cable-stayed Champlain Bridge over the St Lawrence River will have six lanes vehicle lanes and a separate cycle and pedestrian lane. Design life is 125 years and is being constructed under a public-private partnership and operating contract of 30 years after completion of construction. Work includes construction of a smaller bridge for Île des
December 11, 2017 Read time: 3 mins
The 3.4km cable-stayed Champlain Bridge ill have six lanes vehicle lanes and a separate cycle and pedestrian lane (photo courtesy Infrastructure Canada).jpg

The contactor building the replacement Champlain Bridge in Canada has hit back over of allegations of poor workmanship in the US$3.3 billion project.

The new 3.4km cable-stayed Champlain Bridge over the St Lawrence River will have six lanes vehicle lanes and a separate cycle and pedestrian lane. Design life is 125 years and is being constructed under a public-private partnership and operating contract of 30 years after completion of construction.

Work includes construction of a smaller bridge for Île des Soeurs - Nun’s Island - and widening Autoroute 15 through the centre of Montreal.

Infrastructure Canada, an agency of the federal Canadian government, is the client. Construction started in June 2015 and the bridge is on target for opening in December next year, according to SSL. Annual traffic is estimated to be round 60 million vehicles because the bridge is part of a major route into the US.

Recent media reports have suggested the SSL has had problems with poor welding, misaligned holes on steel sections and cracked steel plates.

Daniel Genest, director of co-ordination for the project, said all material meets strict quality standards. Most of the material is being built in factories in the Quebec province cities of Trois-Rivières, Quebec City, Terrebonne and also in Madrid, Spain. Genest said every piece that arrives on site is thoroughly inspected by engineers working for subcontractors.

Further inspections are carried out by an independent engineer hired by Infrastructure Canada and SSL. Infrastructure Canada also does testing on some material in its own lab.

Genest acknowledged that inspection had found problem with some material but the vast majority were minor and easily corrected.

He said that there were around 3,000 reports of “non-conformity” to standards of which 2,500 were related to the bridge and the rest to a section of Autoroute 15. There were 82 parts identified as having major defects, Genest said.

“It’s normal in the sense that if you don’t have [non-conformity reports] in place, it means you don’t have a good quality-control system,” he said.

SSL includes: SNC-Lavalin, ACS Infrastructure, Dragados Canada, Flatiron Constructors Canada and EBC. TY Lin International is lead designer.

The old steel truss and cantilever Champlain Bridge opened in 1962 after five years of construction. Traffic on the six-lane 3.4km structure is around 160,000 vehicles a day. It was built by Atlas Construction, McNamara (Quebec), Key Construction, Deschamps & Bélanger and the Dominion Bridge Company.

In 2013, one lane was closed after a crack was discovered in the superstructure. During emergency repairs, the crack enlarged and a second lane was closed, forcing consideration of building a replacement bridge.

Related Content

  • Acrow supplies temporary bridge during Turcot Interchange project
    June 28, 2018
    Acrow Bridge has supplied a long-term temporary modular bridge to main contractor KPH Turcot for its work on the Turcot Interchange reconstruction in Montréal, Canada. The 32.3m-long Turcot modular steel bridge - Acrow’s longest clear span bridge in Canada – is 5m wide and has an orthotropic deck. The rented Acrow components arrived on site late last year and the bridge was opened to traffic in December. It is expected to be in place for two years. The Turcot Interchange is a three-level stack freeway int
  • Germany plans replacement for A40 Neuenkamp Duisburg Bridge
    March 6, 2018
    Germany’s motorway authority has unveiled plans for an 802m cable stayed replacement bridge taking the A40 over the Rhine River near Duisburg. The state owned authority Deges - Deutsche Einheit Fernstraßenplanungs- und -bau - will oversee the project that includes an eight-lane expansion of the A40, all in the industrial Rhur region.
  • Italy’s horrific bridge collapse is a sign of a wider problem
    January 7, 2019
    The shocking collapse of a major highway bridge in the Italian city of Genoa has highlighted a major problem with regard to poor infrastructure condition in the country. Causing multiple fatalities, the cable-stayed Morandi Bridge suffered a spectacular failure of a central support. Homes have had to be evacuated and it seems likely that the bridge, opened in 1967, will now have to be demolished. However, warnings had been given. The unusual bridge design, with its thin deck and reinforced concrete stays
  • Foundations for Mexico highway with help from Liebherr
    November 9, 2017
    A Liebherr rotary drill rig and oscillator combination has been working in Mexico on a highway project for contractor Mota-Engil. A Liebherr piling rig is playing an important role on a major Mexican highway construction project being carried out by a division of the Portuguese firm Mota-Engil. The use of the rig by Mota-Engil Mexico’s newly formed geotechnical division is helping to set new quality standards for piling in the country. The contractor is leasing one of the latest Liebherr LB 24-270 rotary