South German road tunnel project to restart

Construction work on the Kramertunnel in South Germany is to restart. The tunnel is needed to help reduce traffic delays in the town of Garmisch-Partenkirchen in the southern German state of Bavaria and with lies next to the border with Austria. The twin tube tunnel stretches will both be around 2.8km long and the project will also include building six bridges as part of the new bypass around the town. The new bypass, with its tunnel and bridges, is required as traffic jams occur regularly in the town on th
July 26, 2018 Read time: 2 mins
Construction work on the Kramertunnel in South Germany is to restart. The tunnel is needed to help reduce traffic delays in the town of Garmisch-Partenkirchen in the southern German state of Bavaria and with lies next to the border with Austria. The twin tube tunnel stretches will both be around 2.8km long and the project will also include building six bridges as part of the new bypass around the town. The new bypass, with its tunnel and bridges, is required as traffic jams occur regularly in the town on the existing road. Heavy trucks and holiday traffic crossing the border with Austria can cause congestion.


The project is expected to cost €198 million, with €40 million already having been spent on works carried out so far. Only 350m of the emergency tunnel still needs to be completed. Work commenced in 2010 but was halted in 2013 due to the presence of large quantities of water  in the strata. A new design is being used to cope with the presence of water and the Kramertunnel should be ready for traffic by 2024.

The tunnel sections are being driven using conventional drilling and blasting methods for the hard rock sections comprising around 80% of the length, and with excavators for the looser materials in the remaining 20%. Conventional rock support methods are being used with shotcreting and rock bolting and bolted pre-cast liners. Additional rock support is being used where needed also, while the design now includes extra waterproofing and suitable drainage with collection basins to handle the groundwater and meet environmental requirements. Connecting tunnel sections are located at 500m intervals to meet safety requirements.

Related Content

  • Doka delivers cantilevering for super-slim piers at Lahntal Bridge
    October 21, 2016
    Doka’s formwork expertise is currently in demand during the construction of one of the busiest motorway viaducts in Germany. The 400m six-lane Lahntal Bridge in Limburg dates from the early 1960s. Every day about 100,000 vehicles cross the bridge that spans the valley of the River Lahn. But traffic loads have increased sharply, so a new bridge is being built sited just a few metres west of the old viaduct. The new Lahntal viaduct will measure a massive 43.5m in width, enabling eight lanes plus hard shoul
  • Colorado express lanes opening
    November 29, 2021
    Express lanes are opening on I-25 in Colorado.
  • Traffic control solution manufacturers win key project works
    September 26, 2013
    Traffic control system manufacturers have recently supplied some of their cutting-edge technology to major projects in Europe. Meanwhile, in southern Asia, another leading firm in the sector is helping reduce chronic traffic congestion in Indonesia’s capital, Jakarta. Guy Woodford reports Solutions supplied by Siemens Mobility & Logistics (M&L) are helping the Rijkswaterstaat improve traffic conditions at the Coentunnel in Amsterdam, one of the most heavily used traffic arteries in the Netherlands, used
  • Austria-Slovenia tunnel project awarded
    August 9, 2018
    Construction of the second tube of the Karawanks Tunnel connecting Austria and Slovenia is now going ahead. The work will be headed by Austrian contractors, ARGE Swietelsky Tunnelbau and Swietelsky Baugesellschaft. The 7.8km-long tunnel route runs under the Alpine Karawanks mountain range. The Austrian motorway operator Asfinag is investing around €168 million into the project, while the European Commission is providing €25 million. The work being carried out will include building new rescue routes as wel