South German road tunnel project to restart

Construction work on the Kramertunnel in South Germany is to restart. The tunnel is needed to help reduce traffic delays in the town of Garmisch-Partenkirchen in the southern German state of Bavaria and with lies next to the border with Austria. The twin tube tunnel stretches will both be around 2.8km long and the project will also include building six bridges as part of the new bypass around the town. The new bypass, with its tunnel and bridges, is required as traffic jams occur regularly in the town on th
July 26, 2018 Read time: 2 mins
Construction work on the Kramertunnel in South Germany is to restart. The tunnel is needed to help reduce traffic delays in the town of Garmisch-Partenkirchen in the southern German state of Bavaria and with lies next to the border with Austria. The twin tube tunnel stretches will both be around 2.8km long and the project will also include building six bridges as part of the new bypass around the town. The new bypass, with its tunnel and bridges, is required as traffic jams occur regularly in the town on the existing road. Heavy trucks and holiday traffic crossing the border with Austria can cause congestion.


The project is expected to cost €198 million, with €40 million already having been spent on works carried out so far. Only 350m of the emergency tunnel still needs to be completed. Work commenced in 2010 but was halted in 2013 due to the presence of large quantities of water  in the strata. A new design is being used to cope with the presence of water and the Kramertunnel should be ready for traffic by 2024.

The tunnel sections are being driven using conventional drilling and blasting methods for the hard rock sections comprising around 80% of the length, and with excavators for the looser materials in the remaining 20%. Conventional rock support methods are being used with shotcreting and rock bolting and bolted pre-cast liners. Additional rock support is being used where needed also, while the design now includes extra waterproofing and suitable drainage with collection basins to handle the groundwater and meet environmental requirements. Connecting tunnel sections are located at 500m intervals to meet safety requirements.

Related Content

  • Italian highway bridge and tunnel link
    June 20, 2022
    A project in Central Italy is seeing the construction of new tunnel stretches, a bridge and a viaduct. The work is being carried out on State Road 318 by BESIX in partnership with DONATI, close to Perugia in Umbria.
  • Holiday traffic jams
    October 3, 2018
    In the Northern Hemisphere the summer means time for families to head off on holiday. At this time of year, many busy routes become jammed as holidaymakers head north, south, east or west, all in search of some rest and recreation. In the UK for example, the start of the school holiday period typically leads to families taking to the roads, with massive spikes in traffic volumes as a result. Some areas are particularly bad. The highway routes lying roughly between Munich in southern Germany and Milan in no
  • New Thames River bridge crossing proposed for UK capital London
    July 2, 2014
    Plans are once more being put forward for a new bridge spanning the River Thames in East London. The proposed structure is expected to cost in the region of €750 million (£600 million) to build and has been designed by Arup and HOK. The campaign for the new bridge is being led by the London Chamber of Commerce and Industry (LCCI), which says that there is a desperate need for an additional crossing. The campaign group also has the support of City Airport, which lies on the north side of the Thames and would
  • Tender process for tunnel in Southern Germany
    December 15, 2014
    The tender process is underway for a new tunnel link in the Southern German state of Bavaria.