The contract for the second drive for the Karavanke tunnel connecting Slovenia with Austria is now once more being tendered. The project was awarded earlier this year to the Turkish contractor, Cengiz Insaat Sanayi Ve Ticaret. However this deal was then annulled and the firm prevented from reapplying. The Turkish company had submitted a bid of €89.3 million for the work. However this had to be rejected as the actual estimate to build the link sets a pricetag of some €121.5 million. The Slovenian road opera
December 6, 2018 Read time: 2 mins

The contract for the second drive for the Karavanke tunnel connecting Slovenia with Austria  is now once more being tendered. The project was awarded earlier this year to the Turkish contractor, 4144 Cengiz Insaat Sanayi Ve Ticaret. However this deal was then annulled and the firm prevented from reapplying. The Turkish company had submitted a bid of €89.3 million for the work. However this had to be rejected as the actual estimate to build the link sets a pricetag of some €121.5 million. The Slovenian road operator DARS is now having to choose from the remaining bidders in the original tender offering.

The legal challenge was launched against the tender award by two bidders that were unsuccessful for the project, Kolektor CPG and Euro-Asfalt. The 7.8km-long tunnel route runs under the Alpine Karawanks/Karavanke mountain range, connecting the Austrian Autobahn A11 from Villach with the A2 highway, running across the border to the Slovenian cities of Kranj and Ljubljana.

How many of the original firms bidding for the work are reapplying is unclear and it has not been revealed if those reapplying will make the same offers as before.

In the bidding process earlier this year, a bid of €140 million came from a partnership made up of Slovenian firm Pomgrad and Swiss company Marti. A partnership comprising Implenia Österreich, Implenia Switzerland and Slovenian firm CGP Novo Mesto made a bid of €114.8 million, while a partnership between Slovenian company Gorenjska Gradbena Družba and Czech contractor Metrostav made a bid of €104.4 million. The Slovenian firm GH Holding partnered with Hochtief to bid €118.6 million, meanwhile Slovenian contractor Kolektor CGP partnered with Riko and the Turkish contractor Yapi Merkezijem with a bid of €109.4 million. The Bosnian firm Euroasfalt and the Slovenian company Cestno Podjetje Ptuj bid €106.3 million, meanwhile the Greek contractor J&P Avax offered a bid of €115 million. The Italian contractor Astaldi set up a partnership with the Slovenian companies Cipa and GIC Gradnje and these firms jointly made a bid of €117.5 million.  Completed in 1991, the link suffers heavy congestion at present with traffic
delays frequent at peak periods and during the holiday season.

For more information on companies in this article

Related Content

  • Polish highway deals
    March 2, 2012
    Tenders are being evaluated for a 37km section of the S3 dual carriageway between Gorzow Wielkopolski and Miedzyrzecz in Poland.
  • Polish project tangle unravels?
    February 28, 2012
    The Polish General Directorate of National Roads and Motorways (GDDKiA) is not allowing Chinese firm COVEC to continue construction of A2 highway.
  • Legal step for Czech tunnel project
    April 23, 2014
    The torturous legal case regarding the stalled Blanka Tunnel project in the Czech Republic has taken one step forward. An arbitration court in the country has ruled that the tunnel has to be completed within five months' time. The construction work was halted earlier due to a dispute between the contractor and the city authorities. The tunnel is required to help reduce traffic congestion in the Czech capital Prague with work having commenced in 2007. The project was originally supposed to be ready for traff
  • Slovakia concerned over tenders for D1 Presov and D3 Cadca bypasses
    September 14, 2016
    The Slovakian government is examining bids for two tenders for motorway stretches D1 because of their higher-than-expected costs. The deal involves the Presov West - Presov South stretch and the D3 Cadca, Bukov - Svrcinovec section, according to a report in Pravda. Both projects are bypasses of Cadca, near the border with Poland and the Czech Republic, and Presov in eastern Slovakia. The newly appointed transport minister, Arpad Ersek, review the tenders, the Pravda report said. The Slovak Insti