Slovakia tunnel sections underway but some delays

The route for new tunnel links for Slovakia’s D1 highway has been agreed. New tunnels now look set to be built on the 13.5km stretch between Turany and Hubova section of the D1 highway. This plan calls for the construction of the Korbelka and Havran tunnels at an estimated cost of €900 million. Building these two links would bypass the Lower Fatra mountain range, with the Korbelka Tunnel measuring 5.9km and the Havran Tunnel measuring 2.9km long. The Slovak Environment Ministry rejected an appeal against th
January 23, 2018 Read time: 2 mins
The route for new tunnel links for Slovakia’s D1 highway has been agreed. New tunnels now look set to be built on the 13.5km stretch between Turany and Hubova section of the D1 highway. This plan calls for the construction of the Korbelka and Havran tunnels at an estimated cost of €900 million. Building these two links would bypass the Lower Fatra mountain range, with the Korbelka Tunnel measuring 5.9km and the Havran Tunnel measuring 2.9km long. The Slovak Environment Ministry rejected an appeal against the Environmental Impact Assessment (EIA).


However, questions remain over the Cebrat Tunnel, which is located on the 15km section of the D1 highway between Hubova and Ivachnova. The Slovak Transport and Construction Ministry has been warned by the 2465 European Commission (EC) not to carry out any more work to drive this tunnel until the EIA has been completed. As continuing work on the tunnel could affect European funding for other road projects in Slovakia, the Slovak Transport and Construction Ministry wants progress to be delayed for the meantime. A consortium is carrying out the construction of this section of the D1, having been awarded the package of works by the Slovak motorway management company 5891 NDS. But construction work on the Cebrat Tunnel stopped in 2015 following a landslide, which required the route to be changed and extended by 1.6km to measure 3.6km in all. The tunnel was originally expected to cost €227 million but will now cost €288 million and will not be complete until mid-2022 due to the rerouting and anticipated delays over the EIA completion.

Delays have affected the Visnove Tunnel for the D1 highway but it should now be ready by the summer of 2018. This stretch of tunnel will be 7.5km long and feature parallel drives and work on this section commenced in 2014. It is being built by Salini Impregilo and Duha and is costing around €492 million. The link forms part of a 13.5km stretch of the D1 running through Lietavska Lucka, Visnove and Dubna Skala.

For more information on companies in this article

Related Content

  • Slovakia’s troubled D1 highway
    February 20, 2012
    Slovakia’s Ministry of Transport is to finance construction work on the 75km section of D1 highway between Martin and Presov from state funds, with work expected to start in the second quarter of 2011.
  • Slovakia pushes ahead with the R4 Presov northern bypass
    September 27, 2017
    Slovakia’s national motorway company NDS said it would tender the second stage of the 10.2km R4 Presov northern bypass during the first half of 2018. The project is estimated to be worth around €314 million.
  • Delay for Tvrdosin-Nizna R3 section in Slovakia
    June 22, 2023
    The NDS agency has not reported by how much the contracted cost of €62 million will rise.
  • Slovakia highway construction deal signed
    April 12, 2017
    Plans are now going ahead in Slovakia for a key stretch of the D1 highway project. This 8km Presov West-Presov South section will cost €356 million to construct. The project will be carried out by the D1 Presov Consortium. The project partners in the consortium comprise Eurovia SK, Eurovia CS, Doprastav, Metrostav and Metrostav Slovakia. The agreement with the consortium was reached with Slovakia's National Highway Company (NDS), which awarded the package of works. Construction will commence in June 2017 an