Second giant moveable scaffolding system set for Mersey Gateway

A second movable scaffold system (MSS) is on its way from China to the UK town of Halton, as part of the Mersey Gateway Project, a toll bridge over the Mersey River in England. The machine will be used to build the south elevated approach viaduct that will connect the main road network in the town of Runcorn to the Mersey Gateway Bridge, now under construction.
May 4, 2016 Read time: 3 mins

A second movable scaffold system (MSS) is on its way from China to the UK town of Halton, as part of the 6126 Mersey Gateway Project, a toll bridge over the Mersey River in England.

The machine will be used to build the south elevated approach viaduct that will connect the main road network in the town of Runcorn to the Mersey Gateway Bridge, now under construction.

The new MSS, due to arrive next month, is the same specification as Trinity, the first MSS machine that is building the north approach viaduct in the town of Widnes. Halton schools have been invited to take part in a competition to name the second machine, which will start work on the south approach viaduct in September.

When fully assembled, the latest MSS will measure 157m long - the length of around one and a half football pitches - 8m high and 22m across at its widest point. And at 1,700tonnes, the steel structure will weigh the equivalent of 140 double decker buses.

No UK company has the capacity to design, build and operate a machine of this specification so Merseylink has had them built in China.

Workers will begin to assemble the MSS on site at Astmoor, a suburb of Runcorn, in the summer. It will be erected around the first pier of the approach viaduct, about 12.5m above the ground.

Construction joint venture Merseylink decided to deploy an additional MSS machine to save valuable time dismantling, then transporting and reassembling Trinity on the south side of the river.

Work started on site in May 2014 to build the six-lane toll bridge that is scheduled to open in the autumn of 2017. As well as construction of the bridge, works include upgrading 7km of highway to the north and south of the river - the main bridge is 2.2km long – and changing traffic flow so the majority of traffic uses the new bridge.

The reinforced concrete deck span was revealed when Trinity moved to its second casting position. It was the first of 11 spans that will eventually be cast by the MSS for the deck of the elevated approach viaduct on the north side of the River Mersey.

The span connects the beginning of the approach viaduct from the north abutment in Widnes to the first supporting pier. It measures around 60m long and 18m wide and is angled at 5 degrees to allow vehicles to travel safely around the curve of the approach road.

“Bringing in another MSS will provide additional resilience and ensure that we remain on track to open the new bridge in autumn 2017," said Richard Walker, project director at Merseylink.

To read a World Highways report on Trinity, %$Linker: 2 Internal <?xml version="1.0" encoding="utf-16"?><dictionary /> 2 26084 0 oLinkInternal click here WH report on Trinity false /sections/eurofile/features/first-deck-span-completed-for-mersey-gateways-north-approach-viaduct/ false false%>.

For more information on companies in this article

Related Content

  • PERI’s VARIOKIT as cantilever equipment takes to bauma stage
    February 13, 2013
    PERI’s VARIOKIT engineering construction kit, being showcased at bauma, is said by the German firm to have already provided cost-effective and flexible solutions for superstructures for several years. From project-specific solutions for tunnels, to system applications in bridge construction and heavy-duty towers for the highest loads, VARIOKIT is extremely adaptable. Now it can also be used for the balanced cantilever method with a few additional, newly developed system components. The new components for t
  • Innovative, flexible bridge formwork systems
    February 14, 2012
    Innovative formwork systems have been used to construct a variety of bridge structures. Patrick Smith reports. As part of the work on Germany's new A4 autobahn near Eisenach, the contracting joint venture awarded the formwork contract for two of the three viaducts to Doka. What makes this assignment so special to the company is that although the two steel composite bridges each have very different cross-sections, the JV is using the same overslung composite forming carriage to pour the carriageway slabs of
  • JCB’s new India factory complex
    January 6, 2017
    JCB is to open a new India production factory complex as part of an ambitious global manufacturing and sales growth strategy. Speaking during JCB’s Conexpo 2014 press conference, JCB ceo Graeme Macdonald said, “We continue to invest for our future. Following the 2012 opening of our US$100 million factory in Brazil, we’re now planning to open later this year JCB’s $100 million factory complex in Jaipur – our fourth in India. It’s actually two factories, covering 700,000 square foot on a 114-acre site. It’s
  • JCB’s new India factory complex
    March 6, 2014
    JCB is to open a new India production factory complex as part of an ambitious global manufacturing and sales growth strategy. Speaking during JCB’s Conexpo 2014 press conference, JCB ceo Graeme Macdonald said, “We continue to invest for our future. Following the 2012 opening of our US$100 million factory in Brazil, we’re now planning to open later this year JCB’s $100 million factory complex in Jaipur – our fourth in India. It’s actually two factories, covering 700,000 square foot on a 114-acre site. It’s