Second giant moveable scaffolding system set for Mersey Gateway

A second movable scaffold system (MSS) is on its way from China to the UK town of Halton, as part of the Mersey Gateway Project, a toll bridge over the Mersey River in England. The machine will be used to build the south elevated approach viaduct that will connect the main road network in the town of Runcorn to the Mersey Gateway Bridge, now under construction.
May 4, 2016 Read time: 3 mins

A second movable scaffold system (MSS) is on its way from China to the UK town of Halton, as part of the 6126 Mersey Gateway Project, a toll bridge over the Mersey River in England.

The machine will be used to build the south elevated approach viaduct that will connect the main road network in the town of Runcorn to the Mersey Gateway Bridge, now under construction.

The new MSS, due to arrive next month, is the same specification as Trinity, the first MSS machine that is building the north approach viaduct in the town of Widnes. Halton schools have been invited to take part in a competition to name the second machine, which will start work on the south approach viaduct in September.

When fully assembled, the latest MSS will measure 157m long - the length of around one and a half football pitches - 8m high and 22m across at its widest point. And at 1,700tonnes, the steel structure will weigh the equivalent of 140 double decker buses.

No UK company has the capacity to design, build and operate a machine of this specification so Merseylink has had them built in China.

Workers will begin to assemble the MSS on site at Astmoor, a suburb of Runcorn, in the summer. It will be erected around the first pier of the approach viaduct, about 12.5m above the ground.

Construction joint venture Merseylink decided to deploy an additional MSS machine to save valuable time dismantling, then transporting and reassembling Trinity on the south side of the river.

Work started on site in May 2014 to build the six-lane toll bridge that is scheduled to open in the autumn of 2017. As well as construction of the bridge, works include upgrading 7km of highway to the north and south of the river - the main bridge is 2.2km long – and changing traffic flow so the majority of traffic uses the new bridge.

The reinforced concrete deck span was revealed when Trinity moved to its second casting position. It was the first of 11 spans that will eventually be cast by the MSS for the deck of the elevated approach viaduct on the north side of the River Mersey.

The span connects the beginning of the approach viaduct from the north abutment in Widnes to the first supporting pier. It measures around 60m long and 18m wide and is angled at 5 degrees to allow vehicles to travel safely around the curve of the approach road.

“Bringing in another MSS will provide additional resilience and ensure that we remain on track to open the new bridge in autumn 2017," said Richard Walker, project director at Merseylink.

To read a World Highways report on Trinity, %$Linker: 2 Internal <?xml version="1.0" encoding="utf-16"?><dictionary /> 2 26084 0 oLinkInternal click here WH report on Trinity false /sections/eurofile/features/first-deck-span-completed-for-mersey-gateways-north-approach-viaduct/ false false%>.

For more information on companies in this article

Related Content

  • Kosovo motorway wins IRF award
    May 30, 2013
    Kosovo’s Route 7 Motorway is an 84km dual carriage motorway that will span Kosovo from the southwest border with Albania to the capital city of Pristina, tying the heart of Kosovo to the Albanian port city of Durres. This motorway is part of the pan-European motorway network for Southeast Europe and provides a key trade corridor. In November 2011, Bechtel-Enka General Partnership (BEGP) successfully delivered 38km to the people of Kosovo, only 19 months after the contract award. The second main achievement
  • Innovative concrete pre-casting technology from Exclusivas Resimart Ibérica
    January 6, 2017
    Spanish specialist Exclusivas Resimart Ibérica is developing novel equipment for the production of pre-stressed concrete elements. The company has designed new technologies for pre-cast concrete markets, mainly in precast pre-stressed concrete by vibro-compression technology and extrusion systems.
  • Innovative concrete pre-casting technology from Exclusivas Resimart Ibérica
    March 27, 2013
    Spanish specialist Exclusivas Resimart Ibérica is developing novel equipment for the production of pre-stressed concrete elements. The company has designed new technologies for pre-cast concrete markets, mainly in precast pre-stressed concrete by vibro-compression technology and extrusion systems.
  • PPRS event: Road users’ concerns at the heart of the programme
    December 19, 2014
    Europeans are in two minds about whether their road transport has improved in the past five years, according to the latest European Commission’ Eurobarometer survey and report. According to 38% of respondents, road transport quality had gone up, but 40% said it had dropped, while 18% said there had been no change. Whatever the opinion on quality, 60% of respondents to the report’s survey considered congestion to be the most serious issue facing Europe’s roads. The survey highlighted the dominance o