Second giant moveable scaffolding system set for Mersey Gateway

A second movable scaffold system (MSS) is on its way from China to the UK town of Halton, as part of the Mersey Gateway Project, a toll bridge over the Mersey River in England. The machine will be used to build the south elevated approach viaduct that will connect the main road network in the town of Runcorn to the Mersey Gateway Bridge, now under construction.
May 4, 2016 Read time: 3 mins

A second movable scaffold system (MSS) is on its way from China to the UK town of Halton, as part of the 6126 Mersey Gateway Project, a toll bridge over the Mersey River in England.

The machine will be used to build the south elevated approach viaduct that will connect the main road network in the town of Runcorn to the Mersey Gateway Bridge, now under construction.

The new MSS, due to arrive next month, is the same specification as Trinity, the first MSS machine that is building the north approach viaduct in the town of Widnes. Halton schools have been invited to take part in a competition to name the second machine, which will start work on the south approach viaduct in September.

When fully assembled, the latest MSS will measure 157m long - the length of around one and a half football pitches - 8m high and 22m across at its widest point. And at 1,700tonnes, the steel structure will weigh the equivalent of 140 double decker buses.

No UK company has the capacity to design, build and operate a machine of this specification so Merseylink has had them built in China.

Workers will begin to assemble the MSS on site at Astmoor, a suburb of Runcorn, in the summer. It will be erected around the first pier of the approach viaduct, about 12.5m above the ground.

Construction joint venture Merseylink decided to deploy an additional MSS machine to save valuable time dismantling, then transporting and reassembling Trinity on the south side of the river.

Work started on site in May 2014 to build the six-lane toll bridge that is scheduled to open in the autumn of 2017. As well as construction of the bridge, works include upgrading 7km of highway to the north and south of the river - the main bridge is 2.2km long – and changing traffic flow so the majority of traffic uses the new bridge.

The reinforced concrete deck span was revealed when Trinity moved to its second casting position. It was the first of 11 spans that will eventually be cast by the MSS for the deck of the elevated approach viaduct on the north side of the River Mersey.

The span connects the beginning of the approach viaduct from the north abutment in Widnes to the first supporting pier. It measures around 60m long and 18m wide and is angled at 5 degrees to allow vehicles to travel safely around the curve of the approach road.

“Bringing in another MSS will provide additional resilience and ensure that we remain on track to open the new bridge in autumn 2017," said Richard Walker, project director at Merseylink.

To read a World Highways report on Trinity, %$Linker: 2 Internal <?xml version="1.0" encoding="utf-16"?><dictionary /> 2 26084 0 oLinkInternal click here WH report on Trinity false /sections/eurofile/features/first-deck-span-completed-for-mersey-gateways-north-approach-viaduct/ false false%>.

For more information on companies in this article

Related Content

  • Oerlikon is offering an array of new machine drive technologies
    March 11, 2013
    From Oerlikon’s drive brands Oerlikon Graziano and Oerlikon Fairfield comes an array of sophisticated new drive systems for an array of construction machinery applications. The GA rear axle system is a new generation of motor grader axles specifically designed with a complete tandem box. Wet disc brakes are fitted outboard on each wheel hub, which optimises braking performance, provides easier cooling and also meets international safety regulations. The firm’s axle range for graders includes of five differe
  • Missouri’s Blanchette Bridge gets smaller and smaller
    December 10, 2012
    Missouri’s Blanchette Bridge is now even more abridged. Just a few weeks after explosives took out the West Struss Span, the remaining steel truss on the bridge’s westbound lanes was blown up by demolition crews on Tuesday December 5, 2012. More than 2,000tonnes of steel dropped over 300m into the Missouri River. A 107m section of the Blanchette Bridge was brought down last month. The Blanchette Bridge blasting is part of a US$63 million, year-long project to replace the westbound span.
  • Export intention for Lonking
    January 6, 2017
    Lonking plans to ramp up export levels – Mike Woof reports For Lonking, wheeled loaders form a major part of the firm’s business, although the company now has a well-diversified range. Product development has been important for the company and the third generation wheeled loaders are now coming to market. These new models feature new engines, while the firm is also introducing its second generation excavators and third generation forklift trucks. The third generation wheeled loaders will be available with e
  • Export intention for Lonking
    November 26, 2012
    Lonking plans to ramp up export levels – Mike Woof reports For Lonking, wheeled loaders form a major part of the firm’s business, although the company now has a well-diversified range. Product development has been important for the company and the third generation wheeled loaders are now coming to market. These new models feature new engines, while the firm is also introducing its second generation excavators and third generation forklift trucks. The third generation wheeled loaders will be available with e