Second giant moveable scaffolding system set for Mersey Gateway

A second movable scaffold system (MSS) is on its way from China to the UK town of Halton, as part of the Mersey Gateway Project, a toll bridge over the Mersey River in England. The machine will be used to build the south elevated approach viaduct that will connect the main road network in the town of Runcorn to the Mersey Gateway Bridge, now under construction.
May 4, 2016 Read time: 3 mins

A second movable scaffold system (MSS) is on its way from China to the UK town of Halton, as part of the 6126 Mersey Gateway Project, a toll bridge over the Mersey River in England.

The machine will be used to build the south elevated approach viaduct that will connect the main road network in the town of Runcorn to the Mersey Gateway Bridge, now under construction.

The new MSS, due to arrive next month, is the same specification as Trinity, the first MSS machine that is building the north approach viaduct in the town of Widnes. Halton schools have been invited to take part in a competition to name the second machine, which will start work on the south approach viaduct in September.

When fully assembled, the latest MSS will measure 157m long - the length of around one and a half football pitches - 8m high and 22m across at its widest point. And at 1,700tonnes, the steel structure will weigh the equivalent of 140 double decker buses.

No UK company has the capacity to design, build and operate a machine of this specification so Merseylink has had them built in China.

Workers will begin to assemble the MSS on site at Astmoor, a suburb of Runcorn, in the summer. It will be erected around the first pier of the approach viaduct, about 12.5m above the ground.

Construction joint venture Merseylink decided to deploy an additional MSS machine to save valuable time dismantling, then transporting and reassembling Trinity on the south side of the river.

Work started on site in May 2014 to build the six-lane toll bridge that is scheduled to open in the autumn of 2017. As well as construction of the bridge, works include upgrading 7km of highway to the north and south of the river - the main bridge is 2.2km long – and changing traffic flow so the majority of traffic uses the new bridge.

The reinforced concrete deck span was revealed when Trinity moved to its second casting position. It was the first of 11 spans that will eventually be cast by the MSS for the deck of the elevated approach viaduct on the north side of the River Mersey.

The span connects the beginning of the approach viaduct from the north abutment in Widnes to the first supporting pier. It measures around 60m long and 18m wide and is angled at 5 degrees to allow vehicles to travel safely around the curve of the approach road.

“Bringing in another MSS will provide additional resilience and ensure that we remain on track to open the new bridge in autumn 2017," said Richard Walker, project director at Merseylink.

To read a World Highways report on Trinity, %$Linker: 2 Internal <?xml version="1.0" encoding="utf-16"?><dictionary /> 2 26084 0 oLinkInternal click here WH report on Trinity false /sections/eurofile/features/first-deck-span-completed-for-mersey-gateways-north-approach-viaduct/ false false%>.

For more information on companies in this article

Related Content

  • Bentley announces finalists for the 2017 Be Inspired Awards
    August 11, 2017
    AECOM, Arcadis-WSP/PB, CH2M-Fairhurst and Highways England are among the finalists for this year’s Bentley awards for outstanding use of BIM – building information modelling. Bentley Systems, a provider of infrastructure software solutions, said that the winners will be announced at The Year in Infrastructure 2017 Conference to be held in Singapore this year, October 10-12. “The annual awards honour the extraordinary work of Bentley users advancing infrastructure design, construction, and operations through
  • High court drama expected at Highways UK event, NEC, Birmingham
    November 7, 2016
    What happens when a highways services employee is prosecuted for failing to follow established safety procedures? How would a courtroom drama unfold for the accused and the employer?
  • Successful explosive demolition of old bridge in US state of Missouri
    December 16, 2013
    A successful explosive demolition has been carried out of the Hurricane Deck Bridge in the US state of Missouri. The Hurricane Deck Bridge carried Missouri Route 5 over Lake of the Ozarks and measured 695m long. The structure was no longer able to cope with the traffic volumes it was carrying and the Missouri Department of Transport (MODOT) opted to build a new delta frame bridge to replace it. Work started on the new bridge in 2012 and this was opened to traffic in September 2013. The steel span Hurricane
  • Start of Torrens section upgrade of Adelaide’s North-South Corridor
    August 12, 2015
    Work is underway in the Australian city of Adelaide on a US$657 million upgrade of the Torrens Road to River Torrens section of the North-South Corridor. Nearly 500 workers will eventually be on site to upgrade the 3.7km section of road, of which 3km will be made into a non-stop roadway. The project includes a 2km section of non-stop lowered motorway as well as an overpass for the city’s Outer Harbour rail line. Contractors will deliver six intersection upgrades as well as improved cycling and pedestr