Scotland’s Queensferry Crossing to open in summer 2017?

If good weather conditions continue then Scotland’s new Queensferry Crossing should open to traffic between July and August of this year. The bridge had originally been intended to be ready by December 2016 but construction work was delayed due to tough weather conditions.
May 31, 2017 Read time: 1 min
The new Queensferry Crossing, seen here at an earlier stage of construction, was originally intended to open to traffic in late 2016 but tough weather conditions delayed the opening
If good weather conditions continue then Scotland’s new Queensferry Crossing should open to traffic between July and August of this year. The bridge had originally been intended to be ready by December 2016 but construction work was delayed due to tough weather conditions. However in recent months the weather has been less challenging and has allowed work to continue.


The £1.35 billion project to replace the Forth Road Bridge has been required due to heavy wear and tear the existing structure has suffered from carrying significantly more and heavier traffic than it was designed for. There have also been concerns over corrosion in the main cables of the existing suspension bridge, although further corrosion was halted by the introduction of a novel de-humidification process.

Opening the new Queensferry Crossing will allow the existing Forth Road Bridge to be used as a public transport corridor for buses and taxis. There are also possible plans for the existing bridge to carry trams in the future.

Related Content

  • Resolution for delayed Texas bridge project
    October 23, 2023
    A resolution has been reached for a massive Texas bridge project.
  • ACE/AECOM report: private sector and user-pay for English roads
    May 14, 2018
    It’s one minute to midnight for funding England’s roads, according to a timely new report, and the clock’s big hand is pointing to some form of user-pay solution, reports David Arminas Is there any way out of future user-pay funding for England’s highway infrastructure? The answer is a resounding ‘no’, according to the recently published report: Funding Roads for the Future. The brief 25-page document by the London-based Association for Consultancy and Engineering, ACE**, sums up the state of England’s ro
  • Norway drops tender plans for second Sotra fixed link
    February 18, 2019
    Statens Vegvesen, the Norwegian Road Administration, has cancelled tender plans for a new Sotra fixed link project that were scheduled for the spring. Jon Georg Dale, minister of transport, recently told the Norwegian Parliament that the geology near Lake Storavatnet along the route of the project, of which the second bridge would be a part, has caused concern among planners. Also, reconstruction of a high-voltage power cable has come under questions. Helge Eidsnes, a regional manager of Statens Vegve
  • Tools for breaking
    February 9, 2012
    Mike Woof reports on equipment developments in the demolition sector. The hydraulic hammer is a tough tool used in a wide array of demolition jobs. Highly versatile, the breaker has evolved from a simple design based on rockdrilling equipment into a sophisticated and reliable piece of machinery. German firm Krupp and French company Montabert were pioneers of the hydraulic breaker, being followed into the market by a growing array of other manufacturers. Early breakers had the unfortunate habit of tearing th