RINA Consulting starts to lower Morandi Bridge sections

Deconstruction of the collapsed Morandi Bridge in Genoa, Italy, has begun, according to RINA Consulting. The first bridge deck section was lowered to the ground from a height of 48m, said Roberto Carpaneto, chief executive of RINA which is responsible for design control and construction management of the project. "We are really satisfied with how this delicate operation is being conducted with the whole construction team working as one to guarantee the best result.” RINA Consulting was chosen by the c
February 14, 2019 Read time: 2 mins

Deconstruction of the collapsed Morandi Bridge in Genoa, Italy, has begun, according to RINA Consulting.

The first bridge deck section was lowered to the ground from a height of 48m, said Roberto Carpaneto, chief executive of RINA which is responsible for design control and construction management of the project. "We are really satisfied with how this delicate operation is being conducted with the whole construction team working as one to guarantee the best result.”

RINA Consulting was chosen by the commissioning structure for project management, construction supervision, health and safety overview and quality assurance during the execution phase of the bridge’s demolition and the construction of the new one on the Polcevera valley.

The new 1.1km bridge has been designed by Renzo Piano and will be more than 45m high. The bridge should be open to traffic my mid 2020.

RINA provides services across the energy, marine, certification, transport and infrastructure sectors. Turnover in 2017 was €437 million and the group has around 3,700 employees and 170 offices in 65 countries.

 The longest span of the 1.18km bridge was 210m and the structure had a 40m clearance above the river Polcevera. It was opened in 1967 officially as the Polcevera Viaduct and was part of the A10 motorway as well as European route E80.

It featured diagonal cable-stays with vertical trestle-like supports made up of sets of Vs. One set carrying the roadway deck, while the other pair of inverted Vs supported the top ends of two pairs of diagonal stay cables.

The bridge was closed to traffic in August last year after the longest span collapsed during a major storm, killing 43 people. The bridge had a history of high maintenance costs.

Related Content

  • €1 billion tunnel for Genoa port
    March 6, 2024
    Construction is underway for Genoa’s €1 billion port tunnel.
  • Almost gone: Canada’s old Port Mann Bridge deconstructed
    August 14, 2015
    Three years ago a welder’s cut halved Canada’s old Port Mann Bridge. David Arminas reports from the banks of the Fraser River. By the time this issue of World Highways reaches you, one of Canada’s iconic steel arch bridges will be a shadow of its former self. It’s been a three-year demolition job since the first cut across the deck of the old Port Mann Bridge just outside the city of Vancouver on Canada’s Pacific coast. A new 10-lane 2.2km Port Mann Bridge opened in 2012 (see box). It runs parallel to the o
  • Piers completed for Morandi Bridge replacement project
    February 20, 2020
    The last of the 18 elliptical 40m-tall piers have been finished.
  • New Genoa bridge project underway
    October 18, 2019
    Work is continuing in the Italian city of Genoa on the massive bridge replacement project. The 50m sections of the new bridge deck are now being raised into place using heavy lifting cranes. The deck sections weigh around 500tonnes apiece and measure 50m long, with 18 of these components being required in all. The bridge replacement work is necessary following the horrific collapse of the old Morandi Bridge during 2018, which involved multiple fatalities. The new bridge was designed by Renzo Piano and the w