Restart for Slovakia’s Čebrať tunnel and Hubova-to-Ivachnova D1 section

Work will restart on the 15.2km D1 bypass around the Slovakian town of Ružomberok after the government and contractors amended the contract. The consortium of OHL ZS and Vahostav-SK and the National Highway Company (NDS) recently signed and addendum to the contract that includes an extension of section’s Čebrať tunnel by1.6km to 3.6km and shortening of the road by around 300m. Because of continuing geological concern, NDS had earlier decided to reroute the road and the tunnel. As a result, the cost of the
December 13, 2017 Read time: 2 mins

Work will restart on the 15.2km D1 bypass around the Slovakian town of Ružomberok after the government and contractors amended the contract.

The consortium of OHL ZS and Vahostav-SK and the National Highway Company (5891 NDS) recently signed and addendum to the contract that includes an extension of section’s Čebrať tunnel by1.6km to 3.6km and shortening of the road by around 300m. Because of continuing geological concern, NDS had earlier decided to reroute the road and the tunnel.

As a result, the cost of the D1 section (Hubova to Ivachnova motorway) has risen by €61 million to €227 million.

Work was suspended after a landslide in 2015. The newly estimated opening date of the section is 2022, five years late, according to the Spector newspaper.

Builders will be able to start work on the suspended parts of the motorway - including the Čebrať tunnel, immediately after an environmental impact assessment is finished at the end of January, assuming there are no appeals.

Ružomberok, with a population of around 45,000 including its surrounding area, is in the Liptove region in northern Slovakia. It lies around 260km from the Slovakian capital Bratislava.

For more information on companies in this article

Related Content

  • CT Ictas and Astaldi submit complaint over Peljeski Bridge award
    February 14, 2018
    Croatian media are reporting a dispute between two consortia and that of the China Road and Bridges over the Peljeski bridge project. Croatia’s national roads company Hrvatske Ceste chose China Road and Bridges but the decision is being challenged by a consortium led by the Italian firm Astaldi and one by Turkish CT Ictas. The two consortia submitted their complaints to the Croatian State Commission for Control of Public Ordering Processes in January only days after similar action by another consortia led
  • Slovakia looking for more road financing
    June 13, 2017
    The Slovak government is exploring options for road financing after 2020, according to the media.
  • Stockholm tunnel section awarded
    November 21, 2017
    Contractor STRABAG will construct an additional section of road tunnel for Stockholm’s new bypass project. The contract is worth around €45 million and involves building two parallel bores with a total length of 2.5km for the Akalla tunnel section. The Stockholm bypass runs around the Swedish capital and is currently the largest road construction and tunnelling project in the country. The parallel tunnel bores will both be around 1.23km long and will be driven using conventional drilling and blasting
  • New Macedonia highway section opening
    April 30, 2018
    A new highway stretch measuring 28km long is opening in Macedonia. The work has been carried out by the Greek contractor Aktor. The project has cost €227 million. The new highway section runs from Demir Kapija to Smokvica. Financing has been provided jointly by the European Bank for Reconstruction and Development (EBRD), the European Investment Bank (EIB), a number of funds and also by Macedonia’s own budget. The completion of this section of highway now completes the route connecting the north and south of