Restart for Slovakia’s Čebrať tunnel and Hubova-to-Ivachnova D1 section

Work will restart on the 15.2km D1 bypass around the Slovakian town of Ružomberok after the government and contractors amended the contract. The consortium of OHL ZS and Vahostav-SK and the National Highway Company (NDS) recently signed and addendum to the contract that includes an extension of section’s Čebrať tunnel by1.6km to 3.6km and shortening of the road by around 300m. Because of continuing geological concern, NDS had earlier decided to reroute the road and the tunnel. As a result, the cost of the
December 13, 2017 Read time: 2 mins

Work will restart on the 15.2km D1 bypass around the Slovakian town of Ružomberok after the government and contractors amended the contract.

The consortium of OHL ZS and Vahostav-SK and the National Highway Company (5891 NDS) recently signed and addendum to the contract that includes an extension of section’s Čebrať tunnel by1.6km to 3.6km and shortening of the road by around 300m. Because of continuing geological concern, NDS had earlier decided to reroute the road and the tunnel.

As a result, the cost of the D1 section (Hubova to Ivachnova motorway) has risen by €61 million to €227 million.

Work was suspended after a landslide in 2015. The newly estimated opening date of the section is 2022, five years late, according to the Spector newspaper.

Builders will be able to start work on the suspended parts of the motorway - including the Čebrať tunnel, immediately after an environmental impact assessment is finished at the end of January, assuming there are no appeals.

Ružomberok, with a population of around 45,000 including its surrounding area, is in the Liptove region in northern Slovakia. It lies around 260km from the Slovakian capital Bratislava.

For more information on companies in this article

Related Content

  • EU Cohesion Fund invests in Slovakia D1 motorway
    September 4, 2019
    The European Cohesion Fund is investing nearly €279 million in construction of the west-south deviation of the D1 motorway in Slovakia. The EU-funded works include construction of a two-way tunnel, two interchanges, 12 retaining walls, noise barriers and 18 bridges. The 515km cross-country D1 connects the capital Bratislava, along the Danube River close the country’s western border with the Czech Republic, and in the eastern city of Košice. An extension is proposed from Košice to Michalovce, further
  • Duha and Salini Impregilo to build Slovakia D1 motorway stretch
    April 23, 2014
    Slovak national motorway company NDS has chosen the consortium consisting of fellow Slovak construction company Duha and Salini Impregilo of Italy as the winner of the public procurement tender to build a 13km stretch of the D1 motorway. The Lietavska Lucka-Visnove-Dubna Skala stretch of Slovakia’s D1 includes the 7.5km long Visnove tunnel and is a tender worth nearly €410 million. It is expected that Skanska and Doprastav, which were excluded from the competition, will appeal against NDS' tender award dec
  • Slovakian road protests likely over missing D3 sections
    September 1, 2017
    More road blockades are likely after Slovakia’s state motorway company NDS announced it will not tender for missing sections of the D3 motorway this year. Residents of some towns have blocked sections of roads this year urging the government to speed construction of the D3 to help; boost their local economies, according to Slovakian media.
  • Consortium of Metrostav to build R2 Mytna stretch in Slovakia
    July 4, 2019
    Slovakia’s motorway company NDS has selected a consortium led by Metrostav of the Czech Republic to build a 13.5km stretch of the R3 The cost of the R3 carriageway between Mytna and Tomasovce in the region of Lucenec will be just under €128 million. Other members of the consortium include Prague-based Hochtief CZ and Bratislava-based Hochtief SK and work should start this summer for completion in two years. NDS reported that it had received six bids for the project which went to tender in February 201