Refurbishing Heathrow road tunnel

A Positioner-Actuator-Manipulator (PAM)machine on hire from UK dealer STM of Tring has been able to cut concrete removal time for Bam Nuttall on its €116.2 million tunnel refurbishment contract at Heathrow Airport. The 18-month contract involves major work on the main and cargo tunnels serving Terminals 1, 2 and 3 in order to comply with the latest European standards and also to extend the life of the tunnels for a further 60 years. As part of the project, some 206m2 of concrete repairs were needed to be
December 11, 2015 Read time: 2 mins
The Canadian built PAM unit was used for the Heathrow Tunnel refurbishment
A Positioner-Actuator-Manipulator (PAM)machine on hire from UK dealer STM of Tring has been able to cut concrete removal time for 3137 Bam Nuttall on its €116.2 million tunnel refurbishment contract at Heathrow Airport. The 18-month contract involves major work on the main and cargo tunnels serving Terminals 1, 2 and 3 in order to comply with the latest European standards and also to extend the life of the tunnels for a further 60 years.

As part of the project, some 206m2 of concrete repairs were needed to be carried out. Bam Nuttall opted to use the Canadian built PAM unit, which allowed work to continue throughout the 10.30 pm to 5.30 am possession time. The breaker is firmly secured to an air-over-hydraulic powered two-piece arm, which isolates vibration from the PAM's controls. The unit is mounted on four castors or removable road wheels and can be pushed into position prior to applying the brake and deploying outrigger legs for stability during operation. Weighing only 525kg without a tool in place, the machine can be easily transported in a conventional van.

For more information on companies in this article

Related Content

  • Rammer hammer helps break up rock in Malaysia
    January 19, 2016
    A Rammer 5011 rock breaker has been successfully used to break extremely hard granite on a Kuala Lumpur development. The excavation and site preparation for a development project in Taman Connaught, Cheras, in Kaula Lumpur’s south-eastern suburbs was recently undertaken by local civil engineering contractor, Crescendo Infra Sdn Bhd on behalf of a local developer. In order to deal with the extremely hard granite that was found in the locale, it was initially planned to bring in a blasting contractor to help
  • Bitumen technology ideal for road repairs
    July 4, 2012
    Mike Woof discusses some novel developments relating to bitumen In the developed countries of Western Europe there is an increasing shift away from new highway construction to maintaining and rebuilding existing roads. In Germany alone, a network of asphalt roads extending more than 600,000km will have to be maintained or repaired. Highway maintenance techniques do vary between European countries but some commonalities exist. There are techniques that have been sidelined in the last few years but which now
  • Runway refurbishment at Leipzig/Halle airport
    May 4, 2022
    Leipzig/Halle airport in Germany is now benefiting from a newly rehabilitated runway as well as a number of taxiways
  • Multiple roles for compact construction machines
    February 24, 2012
    Versatility remains the key for the utility equipment sector. The range of duties that compact machines can be used for continues to grow.