Progress on Serbia’s Zezeljev bridge replacement is slow

Construction of the Zezeljev rail and road bridge across the Danube River is facing further delays, according to the Serbian government. Work on the 470m-long new bridge was supposed to be finished by this month. But national elections and changes of government have hampered progress, Serbian media have reported. The original bridge was completed in 1961 as a single-track railway line and separate roadway between the cities of Novi Sad and Petrovaradin. NATO attacked the structure five times during its camp
August 30, 2017 Read time: 2 mins

Construction of the Zezeljev rail and road bridge across the Danube River is facing further delays, according to the Serbian government.

Work on the 470m-long new bridge was supposed to be finished by this month. But national elections and changes of government have hampered progress, Serbian media have reported.

The original bridge was completed in 1961 as a single-track railway line and separate roadway between the cities of Novi Sad and Petrovaradin. NATO attacked the structure five times during its campaign against Yugoslavia, of which Serbia was a member. The bridge was damaged first on 20 April 1999 and finally destroyed four days later, according to Edgar Martin, a waterways transportation consultant working in the Balkans.

Construction of the new bridge forms part of an 3287 EU strategy for the Danube Region. The replacement project was delayed initially because of work to remove wreckage of the old bridge in the Danube.

Completion of the bridge is not now likely to be in the spring of next year. Spanish company 5289 Azvi is the contractor and around €30 million of the estimated 60 million has been invested so far.

The minister also expressed concern over slow progress of works on Ub-Obrenovac part of the Corridor 11 motorway.

Serbia’s president Aleksandar Vucichas said he plans to visit the Surcin-Obrenovac section of Corridor 11. China Construction Communication Company began work on the 18km motorway in March 2017, with completion expected by the end of 2019. Value of works is estimated at €208 million, and is financed by China's Exim Bank, while Serbian roads company Putevi Srbije is the investor.

For more information on companies in this article

Related Content

  • Bosnia tags China Shandong to build Banja Luka-Prijedor motorway
    February 16, 2018
    Bosnia’s autonomous Republika Srpska has picked China Shandong International and Technical Cooperation to construct and operate the Banja Luka-Prijedor motorway. Talks with China Shandong start this month for the 25-30 year concession for the 42km motorway. The company will fund construction and then collect tolls as part of repayment, according to media reports. The cost is estimated to be around €298 million and construction finish is expected to be in 2023. In November, Autoputevi RS, Republika Srpska
  • Czech bridge facing demolition over condition concerns
    October 29, 2018
    A bridge located in Prague, capital of the Czech Republic, is facing calls for its demolition. Concern has been expressed over the condition of the Hlavka Bridge, which spans the Vltava River. The bridge carries heavy vehicle traffic as well as trams and is one of the city’s major transport arteries. It was built originally from 1909 to 1912, replacing an earlier wooden structure. It was then rebuilt so as to cope with vehicle traffic and at present carries up to 100,000 vehicles/day, making it one of the b
  • Strasbourg bypass surveys halted over environmental concerns
    September 27, 2017
    Further delays are looming for construction of the western Strasbourg bypass, a controversial toll motorway project in north eastern France. The government is concerned about environmental issues after Arcos, the wholly-owned subsidiary of Vinci responsible for building the bypass, said it was going to carry out field surveys in 1.5 hectares of what many consider environmentally sensitive areas.
  • Chinese funding financing Serbian road development
    May 19, 2017
    A Chinese contractor looks likely to be building sections of the Corridor 11 highway in Serbia. This follows successful discussions between Serbia and China. These relate to the sections of Corridor 11 from Preljina to Pozega and from Pozega to Boljare that lead towards the border with neighbouring Montenegro. Meanwhile discussions are also being held between Serbia and China with regard to the Ruma to Novi Sad highway, which is also known as the Fruskogorski Koridor. The works are expected to be worth €400