Progress on Serbia’s Zezeljev bridge replacement is slow

Construction of the Zezeljev rail and road bridge across the Danube River is facing further delays, according to the Serbian government. Work on the 470m-long new bridge was supposed to be finished by this month. But national elections and changes of government have hampered progress, Serbian media have reported. The original bridge was completed in 1961 as a single-track railway line and separate roadway between the cities of Novi Sad and Petrovaradin. NATO attacked the structure five times during its camp
August 30, 2017 Read time: 2 mins

Construction of the Zezeljev rail and road bridge across the Danube River is facing further delays, according to the Serbian government.

Work on the 470m-long new bridge was supposed to be finished by this month. But national elections and changes of government have hampered progress, Serbian media have reported.

The original bridge was completed in 1961 as a single-track railway line and separate roadway between the cities of Novi Sad and Petrovaradin. NATO attacked the structure five times during its campaign against Yugoslavia, of which Serbia was a member. The bridge was damaged first on 20 April 1999 and finally destroyed four days later, according to Edgar Martin, a waterways transportation consultant working in the Balkans.

Construction of the new bridge forms part of an 3287 EU strategy for the Danube Region. The replacement project was delayed initially because of work to remove wreckage of the old bridge in the Danube.

Completion of the bridge is not now likely to be in the spring of next year. Spanish company 5289 Azvi is the contractor and around €30 million of the estimated 60 million has been invested so far.

The minister also expressed concern over slow progress of works on Ub-Obrenovac part of the Corridor 11 motorway.

Serbia’s president Aleksandar Vucichas said he plans to visit the Surcin-Obrenovac section of Corridor 11. China Construction Communication Company began work on the 18km motorway in March 2017, with completion expected by the end of 2019. Value of works is estimated at €208 million, and is financed by China's Exim Bank, while Serbian roads company Putevi Srbije is the investor.

For more information on companies in this article

Related Content

  • China's Exim Bank to approve US$ 1.1bn to build Serbia’s Corridor 11 motorway
    October 2, 2012
    The Serbian government has reported that it is planning to sign a loan agreement with China's Exim Bank for new loans worth US$ 1.1 billion for construction of the Corridor 11 motorway. Minister of Finance, Mladan Dinkic, said that the loan will be used for construction of the Belgrade-Ljig and Pojate Preljina motorway parts. The contract agreement is due to be signed by the end of 2012 or beginning of 2013. Works are expected to start sometime next year.
  • Concern over Serbian bridge project behind schedule
    August 28, 2014
    There is concern in Serbia over delays to the Zemun-Borca bridge project. Costing some €197 million in total for the bridge and its access roads, the project is due for completion in December 2014. However Serbia’s Ministry of Construction is investigating why the project is not on track and wants to bring the work back into line with the planned schedule. The Serbian Government is funding 15% of the project while China’s Exim Bank is providing 85%. The Chinese contractor China Road and Bridge Corporation i
  • Serbia project for Chinese?
    December 11, 2012
    Serbian Minister of Construction and Urbanism, Velimir Ilic, claims the China Roads and Bridges Company (CRBC) has verbally agreed to invest €2.5 billion (US$ 4.8bn) to enable the construction of the Corridor 11 motorway. Ilic said that an official CRBC offer to fund and build the key motorway route will be submitted from the beginning of September 2012. The CRBC is already participating in construction of Serbia’s Zemun-Bora bridge. Ilic added that the World Bank (WB) had expressed interest in funding a
  • Serbia projects due for completion
    December 14, 2016
    Work is pushing ahead with the construction of the Corridor 10 and Corridor 11 highway projects in Serbia. Sections of the highway projects will be opened to traffic in 2017. All of Corridor 10 will be ready for use while the Obrenovac to Preljina stretch of Corridor 11 will open. Other road projects will commence including links running through Moravski and Fruskogorski. The Serbian Government doubled its infrastructure spending to €608.14 million for 2016, with a substantial portion being provided through