Prague wins legal battle over Blanka Tunnel costs

The Czech capital Prague will not have to pay €63 million to construction firm CKD Praha DIZ for cost overruns on the Blanka Tunnel complex. CKD Praha DIZ sought the amount over an alleged rise in costs when completion of the tunnel was delayed, according to a report by Radio Praha.
September 6, 2016 Read time: 2 mins

The Czech capital Prague will not have to pay €63 million to construction firm CKD Praha DIZ for cost overruns on the Blanka Tunnel complex.

CKD Praha DIZ sought the amount over an alleged rise in costs when completion of the tunnel was delayed, according to a report by Radio Praha.

A court of arbitration also ruled that the company must pay the city’s legal costs of around €630,000. The court’s decisions are binding and final.

The 6.4km Blanka Tunnel complex is a part of Prague’s unfinished ring road system and is the longest road tunnel in the Czech Republic and the longest city tunnel in Europe. Just under 40km of the 83km Ring Road are complete.

The tunnel, which connects the area west of Prague Castle with Trója district in the northeast, consists of three tunnels - Bubenečský, Dejvický and Brusnický. Construction started in 2006 and completion was supposed to be 2011.

However, delays put the opening date back to September last year and doubled the overall cost to around €1.6 billion.

A survey by Prague’s Technical Administration of Roadways recently found that on averages 75,000 vehicles use the Blanka tunnel daily.

Related Content

  • Green credentials a major issue for Italian buyers of equipment
    November 5, 2019
    Some of the main driving forces for purchasing new construction machinery in Italy are better efficiency and green credentials in terms of emissions and noise. Intelligent machines are coming to play an increasingly central role in the sector, according to the new SaMoTer-Veronafiere survey, published ahead of the exhibition set for March. It found that 16% of users and 31% of hire firms believe green credentials are an important criterion when making purchasing decisions. Moreover, almost 4% of users
  • Poland’s A1 section Pyrzowice to Tuszyn clears another hurdle
    November 11, 2014
    The Polish province of Lodzkie has signed a territorial contract that will allow construction of the Pyrzowice to Tuszyn section of the national A1 motorway. Territorial contracts are agreements between the central and regional governments in order to allow investment in key projects, such as roads. Around 90 projects worth in total US$7.63 billion will benefit from the contract. Apart from the 140km A1 motorway section, projects include rail line upgrades, Wielun and Belchatow ring roads hospital extensio
  • Stonehenge Tunnel legal action launched
    December 1, 2020
    Legal action launched against the Stonehenge Tunnel project.
  • New ring road to solve problem of traffic jams in Ukraine capital Kiev
    May 10, 2018
    Ukraine’s capital Kiev will benefit from a new ring road – Eugene Gerden writes The government of Ukraine, together with the authorities of the Ukrainian capital Kiev, plans to invest up to US$2 billion in the building of a new ring road around the city. The new road, known as the Great Ring Road, will be around 200km long, of which 65km will be of existing roads and 148km of new roads. The ring road will connect three international transport corridors that run through the territory of Ukraine, as well