Prague wins legal battle over Blanka Tunnel costs

The Czech capital Prague will not have to pay €63 million to construction firm CKD Praha DIZ for cost overruns on the Blanka Tunnel complex. CKD Praha DIZ sought the amount over an alleged rise in costs when completion of the tunnel was delayed, according to a report by Radio Praha.
September 6, 2016 Read time: 2 mins

The Czech capital Prague will not have to pay €63 million to construction firm CKD Praha DIZ for cost overruns on the Blanka Tunnel complex.

CKD Praha DIZ sought the amount over an alleged rise in costs when completion of the tunnel was delayed, according to a report by Radio Praha.

A court of arbitration also ruled that the company must pay the city’s legal costs of around €630,000. The court’s decisions are binding and final.

The 6.4km Blanka Tunnel complex is a part of Prague’s unfinished ring road system and is the longest road tunnel in the Czech Republic and the longest city tunnel in Europe. Just under 40km of the 83km Ring Road are complete.

The tunnel, which connects the area west of Prague Castle with Trója district in the northeast, consists of three tunnels - Bubenečský, Dejvický and Brusnický. Construction started in 2006 and completion was supposed to be 2011.

However, delays put the opening date back to September last year and doubled the overall cost to around €1.6 billion.

A survey by Prague’s Technical Administration of Roadways recently found that on averages 75,000 vehicles use the Blanka tunnel daily.

Related Content

  • Increased infrastructure spending
    February 22, 2012
    With economies booming in the BRIC countries and other regions, spending on infrastructure is at a high - Patrick Smith reports As economic crisis grips much of the world, many countries are still spending billions on infrastructure to improve transportation. While the USA and Europe struggle with debt problems (and this has affected much of the rest of the world) the development of highways, airport, ports and other infrastructure is gathering pace in other regions to boost economic developments.
  • Vietnam’s North-South Expressway sections
    March 24, 2025
    Key sections of Vietnam’s North-South Expressway are nearly complete.
  • FCC heads group that will build Toyo Tunnel in Colombia
    November 6, 2015
    Spanish environmental services, infrastructure and water group FCC has secured a €392 deal to design, build, operate and maintain the 10km Toyo Tunnel in Urabá Port, Colombia. The Government of Antioquia awarded the project to the consortium in which Madrid-based FCC has a 40% share and a group of local business people hold 60%. The tunnel is around 80km from Medellin, the capital of Colombia’s mountainous Antioquia province. The US$426 million contract is for 10 years, during which design and constru
  • Contracts are about to be signed for the Fehmarnbelt Fixed Link
    March 13, 2015
    Nearly eight years after Denmark and Germany agreed to construct a major undersea road and rail tunnel, the first contracts are about to be signed. David Arminas reports. Construction is due to start later this year on one of Europe’s most ambitious, as well as the world’s longest, road and rail tunnels, the 17.6km Fehmarnbelt Fixed Link between Germany and Denmark. Fehmarnbelt is expected to cost around US$7.5 billion and be five times the length of the Øresund tunnel between the Danish capital Copenhagen