Prague wins legal battle over Blanka Tunnel costs

The Czech capital Prague will not have to pay €63 million to construction firm CKD Praha DIZ for cost overruns on the Blanka Tunnel complex. CKD Praha DIZ sought the amount over an alleged rise in costs when completion of the tunnel was delayed, according to a report by Radio Praha.
September 6, 2016 Read time: 2 mins

The Czech capital Prague will not have to pay €63 million to construction firm CKD Praha DIZ for cost overruns on the Blanka Tunnel complex.

CKD Praha DIZ sought the amount over an alleged rise in costs when completion of the tunnel was delayed, according to a report by Radio Praha.

A court of arbitration also ruled that the company must pay the city’s legal costs of around €630,000. The court’s decisions are binding and final.

The 6.4km Blanka Tunnel complex is a part of Prague’s unfinished ring road system and is the longest road tunnel in the Czech Republic and the longest city tunnel in Europe. Just under 40km of the 83km Ring Road are complete.

The tunnel, which connects the area west of Prague Castle with Trója district in the northeast, consists of three tunnels - Bubenečský, Dejvický and Brusnický. Construction started in 2006 and completion was supposed to be 2011.

However, delays put the opening date back to September last year and doubled the overall cost to around €1.6 billion.

A survey by Prague’s Technical Administration of Roadways recently found that on averages 75,000 vehicles use the Blanka tunnel daily.

Related Content

  • Highway 407 Revisited – smart tollroad extension
    June 7, 2016
    In the late 1990s, World Highways published a supplement on construction of Canada’s Highway 407, the world’s first all-electronic toll road. But how successful has it been? David Arminas reports from Toronto The head office for 407 ETR Concession Company is a low-rise building next to exit 59, just north of Toronto, Canada’s economic powerhouse. The building may be non-descript but inside is the advanced technical heart of Highway 407 ETR – Express Toll Route. It houses the latest toll monitoring techno
  • Poland bidders angry over Astaldi win for Warsaw Ring Road work
    June 18, 2015
    Four groups that made bids for building the southern section of the Warsaw Ring Road have filed complaints about how the national road authority GDDKiA chose Astaldi as the winner. Companies appealing to the National Board of Appeal (KIO) are Impresa Pizzarotti, Porr Polska, Salini Polska and IDS-BUD. The offer made by Italian company Astaldi was at least 25% less than the estimated €391 million cost of the project, according to Polish media reports. World Highways reported in February that Astaldi
  • BC again eyes Massey Tunnel replacement
    December 21, 2020
    The aging 61-year-old Canadian tunnel is about 30km north of the US state of Washington.
  • Ontario’s Highway 407 East Phase 2B extension opens
    January 23, 2020
    The 23km final extension phase of the provincially-owned tolled freeway Highway 407 East near Toronto, Canada has opened.