Prague wins legal battle over Blanka Tunnel costs

The Czech capital Prague will not have to pay €63 million to construction firm CKD Praha DIZ for cost overruns on the Blanka Tunnel complex. CKD Praha DIZ sought the amount over an alleged rise in costs when completion of the tunnel was delayed, according to a report by Radio Praha.
September 6, 2016 Read time: 2 mins

The Czech capital Prague will not have to pay €63 million to construction firm CKD Praha DIZ for cost overruns on the Blanka Tunnel complex.

CKD Praha DIZ sought the amount over an alleged rise in costs when completion of the tunnel was delayed, according to a report by Radio Praha.

A court of arbitration also ruled that the company must pay the city’s legal costs of around €630,000. The court’s decisions are binding and final.

The 6.4km Blanka Tunnel complex is a part of Prague’s unfinished ring road system and is the longest road tunnel in the Czech Republic and the longest city tunnel in Europe. Just under 40km of the 83km Ring Road are complete.

The tunnel, which connects the area west of Prague Castle with Trója district in the northeast, consists of three tunnels - Bubenečský, Dejvický and Brusnický. Construction started in 2006 and completion was supposed to be 2011.

However, delays put the opening date back to September last year and doubled the overall cost to around €1.6 billion.

A survey by Prague’s Technical Administration of Roadways recently found that on averages 75,000 vehicles use the Blanka tunnel daily.

Related Content

  • LagoonHull project put on hold
    February 8, 2023
    The plan by the UK city of Kingston upon Hull is to transform the city centre and river frontage running from the 2.2km-long, single-span suspension Humber Bridge.
  • Scotland’s new Queensferry Crossing over the Forth Estuary
    December 23, 2015
    The new Queensferry Crossing under construction in Scotland will be the third landmark bridge spanning the Forth Estuary - Mike Woof writes When the new Queensferry Crossing over the Forth Estuary opens at the end of 2016, it will be the third landmark bridge to be built spanning this short stretch of water. Lying alongside the existing road bridge and the historic rail bridge, this new structure will be as groundbreaking as the two earlier crossings were at the time of their construction.
  • A new project will tackle Prague’s traffic congestion
    September 21, 2012
    The authorities in Czech capital Prague are looking at option to speed the completion of a new ring road. Constructing the internal ring road on a fast-track basis could cost in the order of €81.5 million (CZK2 billion). Should this move be made the route could be ready to carry traffic by 2015. Prague suffers heavy congestion at peak periods, particularly in the historic city centre.
  • UK report suggests 30km Pennine tunnel with robotic maintenance
    December 2, 2015
    The UK could build one of Europe’s longest road tunnels as it considers route options for a new major link connecting the cities of Manchester and Sheffield in England. An interim report looking at how best to connect the cities suggested that the road could be between 40km-50km, depending on the route. It “will include a tunnelled section, which could range from between 20-30km, making it one of the longest road tunnels ever built”.