Prague wins legal battle over Blanka Tunnel costs

The Czech capital Prague will not have to pay €63 million to construction firm CKD Praha DIZ for cost overruns on the Blanka Tunnel complex. CKD Praha DIZ sought the amount over an alleged rise in costs when completion of the tunnel was delayed, according to a report by Radio Praha.
September 6, 2016 Read time: 2 mins

The Czech capital Prague will not have to pay €63 million to construction firm CKD Praha DIZ for cost overruns on the Blanka Tunnel complex.

CKD Praha DIZ sought the amount over an alleged rise in costs when completion of the tunnel was delayed, according to a report by Radio Praha.

A court of arbitration also ruled that the company must pay the city’s legal costs of around €630,000. The court’s decisions are binding and final.

The 6.4km Blanka Tunnel complex is a part of Prague’s unfinished ring road system and is the longest road tunnel in the Czech Republic and the longest city tunnel in Europe. Just under 40km of the 83km Ring Road are complete.

The tunnel, which connects the area west of Prague Castle with Trója district in the northeast, consists of three tunnels - Bubenečský, Dejvický and Brusnický. Construction started in 2006 and completion was supposed to be 2011.

However, delays put the opening date back to September last year and doubled the overall cost to around €1.6 billion.

A survey by Prague’s Technical Administration of Roadways recently found that on averages 75,000 vehicles use the Blanka tunnel daily.

Related Content

  • Norway’s record breaking undersea road tunnel
    February 25, 2015
    The world's deepest road tunnel is currently in construction near Stavanger in Norway but is only the prelude to even larger projects - report and photographs by Adrian Greeman. Norway's convoluted coastline of fjords and high mountains is famously scenic but also a major problem for transport and connections. The country has long experience of constructing tunnels as a result. Now a series of tunnels underway, or in design, around the oil industry city of Stavanger will stretch its skills more than usual.
  • Ferry operators sink the financing plan for Fehmarn Belt link
    December 17, 2018
    The Court of Justice of the European Union has said Denmark’s state grant aid to the proposed Fehmarn Belt link is illegal under EU rules. The court noted that the European Commission approved the Fehmarn project’s financing – total cost likely around the €8.7 billion - in July 2015 without a formal procedure. Denmark is completely responsible for financing the project that will replace a ferry service. Part of the funds were to come through the European Union and its Connecting Europe Facility for tr
  • Increased costs for new Duisburg bridge
    June 2, 2020
    Increased costs are now being anticipated for the new Duisburg bridge project.
  • Vinci picks up Lafonataine Tunnel work
    August 12, 2020
    The renovated tunnel is expected to have about 40 years of life.