Skip to main content

Paraguay project progressing to plan

Paraguay’s Bi-Oceanic Road project is progressing to plan.
By MJ Woof October 26, 2020 Read time: 1 min
Progress is good for Paraguay’s bi-oceanic corridor project – image © courtesy of Rosevite2000, Dreamstime.com
Construction work for Paraguay’s Bi-Oceanic Road project is progressing to plan. Building of the route is being carried out by a consortium, Consorcio Corredor Vial Bioceanico, which comprises Queiroz Galvao and Ocho A.

So far 106km of the 277km route has been built. The project is costing an estimated US$445 million to construct and the work is being overseen by Paraguay’s Ministry of Public Works and Communications (MOPC).

Related Content

  • Paraguay in talks with Inter-American Development Bank (IADB)
    October 21, 2014
    Paraguay’s Ministry of Public Works and Communications (MOPC) hopes to finalise a US$100 million loan with the Inter-American Development Bank (IADB) for construction of new roads. The loan, expected to be signed at the end of November, will be for construction of around 400km of new roads and 2km of new bridges. Once the loan is signed, MOPC hopes to open tenders for the projects in December. Paraguay also plans to award infrastructure projects for a record $758 million in the last three months of th
  • Paraguay bridge project completion is due
    May 29, 2023
    Completion of a major Paraguay bridge project is due shortly.
  • Paraguay road widening contract
    April 14, 2022
    A Paraguayan road widening contract will be offered.
  • Paraguay to invest US$500mn in roads during 2014
    January 21, 2014
    Paraguay’s Ministry of Public Works and Communications (MOPC) is this year said to be planning to invest US$500 million in the South American country’s roads. The figure is said to be part of a proposed infrastructure investment of $7.66 billion for the period 2013-2016. Among the 2014 road projects will be the estimated $84.46 million repair of Route 8 -72.9kms – put out to tender by the MOPC in December 2013. All bids must be submitted on 29 January 2014. Route number 9 -Transchaco- between Mariscal Est