Paraguay project progressing to plan

Paraguay’s Bi-Oceanic Road project is progressing to plan.
By MJ Woof October 26, 2020 Read time: 1 min
Progress is good for Paraguay’s bi-oceanic corridor project – image © courtesy of Rosevite2000, Dreamstime.com
Construction work for Paraguay’s Bi-Oceanic Road project is progressing to plan. Building of the route is being carried out by a consortium, Consorcio Corredor Vial Bioceanico, which comprises Queiroz Galvao and Ocho A.

So far 106km of the 277km route has been built. The project is costing an estimated US$445 million to construct and the work is being overseen by Paraguay’s Ministry of Public Works and Communications (MOPC).

Related Content

  • Colombia’s delayed La Linea Tunnel and tertiary road development programme seeing progress
    July 6, 2017
    Progress is now being seen in Colombia with regard to key tunnel and road projects. A consortium comprising Conconcreto and CSS Constructores is to complete the 12% of work still needed to finish the La Linea Tunnel project.
  • Paraguay road tenders being planned
    March 3, 2016
    A series of tenders for major road projects is planned in Paraguay during 2016. The country's Ministry of Public Works and Communications (MOPC) will launch tenders with a total value of US$2.27 billion. The Ministry of Public Works and Communications will prioritise works including construction of the first stretch of the Bioceanic corridor, La Costanera Sur road and the 147km-long export corridor. The plans call for projects worth some $1.8 billion to go to tender in the first half of 2016. These projects
  • Paraguay PPP project proposals
    November 26, 2015
    Proposals are expected for widening work to two major highways in Paraguay. In all seven consortia look likely to submit their proposals for the PPP widening project for Route 2 and Route 7. The Directorate of Strategic Projects (DIPE) of Paraguay's Ministry of Public Works and Communications (MOPC) has reported that seven of the eleven pre-qualified firms have shown string interest in the work. The project is due for completion after 2019 and will cost close to $400 million. Bidding for the project will no
  • Plan proposed for Paraguayan programme of bridge replacement
    February 3, 2014
    Work is starting in Paraguay on a programme to construct 100 reinforced concrete bridges. These will replace old wooden structures that have been deemed obsolete and the work is due for completion by the end of 2015. The programme of works is costing US$75 million, with the Paraguayan Government paying $25 million for the work and the remaining $50 million being provided by the Latin American Development Bank (CAF). The project forms part of a much wider $7.66 billion infrastructure investment programme by