Norway drops tender plans for second Sotra fixed link

Statens Vegvesen, the Norwegian Road Administration, has cancelled tender plans for a new Sotra fixed link project that were scheduled for the spring. Jon Georg Dale, minister of transport, recently told the Norwegian Parliament that the geology near Lake Storavatnet along the route of the project, of which the second bridge would be a part, has caused concern among planners. Also, reconstruction of a high-voltage power cable has come under questions. Helge Eidsnes, a regional manager of Statens Vegve
February 18, 2019 Read time: 2 mins
Artist impression of a proposed four-lane Sotra Bridge, a suspension crossing beside the existing two-lane bridge that opened in 1971 (photo courtesy Statens Vegvesen)
1208 Statens Vegvesen, the Norwegian Road Administration, has cancelled tender plans for a new Sotra fixed link project that were scheduled for the spring.


Jon Georg Dale, minister of transport, recently told the Norwegian Parliament that the geology near Lake Storavatnet along the route of the project, of which the second bridge would be a part, has caused concern among planners. Also, reconstruction of a high-voltage power cable has come under questions.

Helge Eidsnes, a regional manager of Statens Vegvesen, said a new project plan will be presented in the summer. The project is intended to be a public-private partnership.

Last May, Parliament approved the €1.03 billion project - priority in the National Transport Plan for 2018–2023 - that included the nearly 1km Sotra Bridge. The signing of the contract was to have been in early 2020, according to the process laid out by Statens Vegvesen.

The proposed four-lane Sotra suspension bridge is 29.5m wide and has a 592m main span with the two towers rising 144m above sea level. A separate pedestrian path and separate cycle lane, both 5m wide, were part of the design.

The project overall has 19 other smaller bridges, 11 overpasses/underpasses and 21 tunnel portals. Around 11 tunnels through the mountains were envisaged, from 1-2km longs. Around 24km of access roads are scheduled with nearly 14km of bicycle and pedestrian paths, around 3m wide.

The new bridge is to be built parallel to the existing two-lane 1.2km concrete suspension Sotra Bridge that opened in 1971. It carries around 22,700 daily, estimated to rise to 26,000 by 2024. It crosses Knarreviksundet (Knarrevik Sound) that separates the island of Litlesotra, part of the Sotra archipelago, from the mainland and the city Bergen.

A new bridge is needed because, according to Statens Vegvesen, over the past 15 years there has been a strong increase in traffic between Sotra and Bergen. But old bridge is vulnerable to high winds and is closed when wind speed exceeds 30m/sec.

For more information on companies in this article

Related Content

  • Key highway project for Norway
    January 9, 2014
    The Norwegian Public Roads Administration, Statens Vegvesen , has awarded contracts for the E6 highway to Implenia and KA Austad and for the E18 south of capital Oslo. The E6 contract relates to the stretch connecting Vinstra and Sjoa in Gudbrandsdalen and is worth some €185.71 million. The construction work is now commencing and will take until October 2016 to complete. The project is for 16km of the E6 however it will include tunnel construction work. Hard, competent rock conditions mean that drill and bl
  • Norway mega-project contract for Fugro
    December 20, 2017
    The largest road project in Norway’s history has seen Fugro win a second major contract from the Norwegian Public Roads Administration (NPRA). The work on the E39 Coastal Highway is for the construction of a 1,100km route from Kristiansand in the south to Trondheim in central Norway. This project is expected cost around €34.4 billion (NOK 340 billion).
  • Pedestrian bridges go-ahead for US-Canada Gordie Howe project
    January 24, 2020
    The Windsor-Detroit Bridge Authority has selected the design for the five pedestrian bridges which will be part of the US$4.4 billion Gordie Howe International Bridge.
  • Transpordiamet opens Tartu procurement
    May 20, 2021
    The Estonian Transport Administration - Transpordiamet - is tendering for the Tallinn–Tartu–Võru–Luhamaa highway section of the planned Western Tartu Bypass.