Skip to main content

New Wear Crossing cables fully installed and tensioned to 50%

Structural engineering company VSL International has installed all 28 cable stays of England’s New Wear Crossing and stressed them to 50% of their design load. The next stage of stressing the cables will happen next month and be to 100% of design load. This will allow the construction team to adjust and tension them just enough to lift the bridge deck off the blue steel temporary supports that were constructed in the river to take the weight of the structure.
September 21, 2017 Read time: 3 mins
Looking good: The 28 cable stays are fully installed on the New Wear Crossing and tensioned to 50 percent.

Structural engineering company 1569 VSL International has installed all 28 cable stays of England’s New Wear Crossing and stressed them to 50% of their design load.

The next stage of stressing the cables will happen next month and be to 100% of design load. This will allow the construction team to adjust and tension them just enough to lift the bridge deck off the blue steel temporary supports that were constructed in the river to take the weight of the structure.
 
In the coming months, the temporary supports will be removed, leaving only the single central arched pylon and the bridge deck on display in the river.

Opening of the bridge is expected by spring of next year.

Finishing works, such as road surfacing, paving, lighting, the installation of railings and carrying out road markings, must all be complete before the cable stays can be finely adjusted and locked off at the end of construction.

 The 28 cable stays are installed in pairs north and south of the central pylon. Each cable stay is contained inside a white protective, plastic sheath. Inside each sheath, or tube, are between 44-77 strands, depending on a cable’s intended position on the deck, that form a single cable. They vary in length from 52-165m.

The longer the cable, the more strands there are. Each strand is the diameter of a small coin and will be tensioned to lift seven tonnes.

“People could be forgiven for thinking the bridge is very close to opening as the structure looks complete from a distance,” explained Stephen McCaffrey, project director for 1622 Farrans Construction and Victor Buyck Steel Construction, a joint venture to deliver the project on behalf of Sunderland City Council.

“We still have quite a lot to do, such as completing the road works on both sides of the river, getting the surface of the bridge deck finished and all of those additional works and safety features complete.”
 
Work began on the New Wear Crossing – Sunderland’s first bridge across the River Wear in more than 40 years – in May 2015.

The bridge become more recognisable with the 105m pylon being erected in February, the bridge deck launched across the river in spring and the installation of the cable stays during the summer.

For more information on companies in this article

Related Content

  • Researchers trial 3D printing for both concrete and asphalt roads
    February 27, 2019
    Automated road repairs, using 3D printing, could save money and vastly reduce disruption, and researchers are already showing it’s possible - Kristina Smith reports It’s the middle of the night, and in the street below a team is busy carrying out repairs to the road surface. But there isn’t a human in sight. A road repair drone has landed at the site of a crack and a 3D asphalt printer is now busy filling in that crack. A group of traffic cone drones have positioned themselves around the repair location
  • Alberta’s peaceful partnership
    May 4, 2020
    A bridge project in northern Canada threw up some unexpected challenges, reports David Arminas, from the banks of the Peace River in Alberta
  • Winning formula for formwork
    July 19, 2012
    An unusual application of formwork took place recently in France, while formwork using one particular engineering construction kit was used for the first time in Poland. Guy Woodford reports An 80m long wild game underpass is an innovative feature of the Route Nationale 88 (RN 88) expansion in south-west France. For construction of the arched underpass tunnel, a PERI tunnel formwork carriage using VARIOKIT engineering construction kit was used. Thanks to the equipment’s easy handling, along with pre-assembl
  • Bold move aids Ironton-Russell bridge works in U.S.
    January 24, 2014
    The bold decision to go against the norm and build the back spans using falsework for the Ironton-Russell replacement bridge between Parkersburg, Kentucky and Cincinnati, Ohio allowed land access to build the main span which, along with the first use in the U.S. of precast stay anchor blocks, meant the new structure could get built.