New Wear Crossing cables fully installed and tensioned to 50%

Structural engineering company VSL International has installed all 28 cable stays of England’s New Wear Crossing and stressed them to 50% of their design load. The next stage of stressing the cables will happen next month and be to 100% of design load. This will allow the construction team to adjust and tension them just enough to lift the bridge deck off the blue steel temporary supports that were constructed in the river to take the weight of the structure.
September 21, 2017 Read time: 3 mins
Looking good: The 28 cable stays are fully installed on the New Wear Crossing and tensioned to 50 percent.

Structural engineering company 1569 VSL International has installed all 28 cable stays of England’s New Wear Crossing and stressed them to 50% of their design load.

The next stage of stressing the cables will happen next month and be to 100% of design load. This will allow the construction team to adjust and tension them just enough to lift the bridge deck off the blue steel temporary supports that were constructed in the river to take the weight of the structure.
 
In the coming months, the temporary supports will be removed, leaving only the single central arched pylon and the bridge deck on display in the river.

Opening of the bridge is expected by spring of next year.

Finishing works, such as road surfacing, paving, lighting, the installation of railings and carrying out road markings, must all be complete before the cable stays can be finely adjusted and locked off at the end of construction.

 The 28 cable stays are installed in pairs north and south of the central pylon. Each cable stay is contained inside a white protective, plastic sheath. Inside each sheath, or tube, are between 44-77 strands, depending on a cable’s intended position on the deck, that form a single cable. They vary in length from 52-165m.

The longer the cable, the more strands there are. Each strand is the diameter of a small coin and will be tensioned to lift seven tonnes.

“People could be forgiven for thinking the bridge is very close to opening as the structure looks complete from a distance,” explained Stephen McCaffrey, project director for 1622 Farrans Construction and Victor Buyck Steel Construction, a joint venture to deliver the project on behalf of Sunderland City Council.

“We still have quite a lot to do, such as completing the road works on both sides of the river, getting the surface of the bridge deck finished and all of those additional works and safety features complete.”
 
Work began on the New Wear Crossing – Sunderland’s first bridge across the River Wear in more than 40 years – in May 2015.

The bridge become more recognisable with the 105m pylon being erected in February, the bridge deck launched across the river in spring and the installation of the cable stays during the summer.

For more information on companies in this article

Related Content

  • The March of the Urban Low-emission Zone
    April 17, 2018
    Europe’s political patchwork is getting a low-emission zone overlap, according to Malcolm Kent* By now, pretty much everybody in the industry will be aware of the Low Emission Zone in London, UK. But awareness of similar European zones about to start or expand might be more patchy. The background to all of these schemes is the problem of air quality, particularly European Union rules setting limits on acceptable pollution levels. It was found some years ago that several member states’ cities, including
  • Motorway's tricky cable installation
    February 6, 2012
    The UK is now benefiting from the installation of sophisticated automated traffic management equipment and information signs on its motorway network. But with heavy traffic volumes on these roads, novel techniques have had to be implemented. One such operation, organised by client The Highways Agency and its consulting engineer A.One+, has recently been underway on the M56 motorway between Junctions 9 and 16 in north-west England under the Triple Package Advanced Works designation. To minimise traffic distu
  • Award winning bridge a' masterpiece of architecture'
    April 10, 2012
    Mega project of “extreme beauty” receives top award from the IRF, writes Patrick Smith.The Sheikh Zayed Bridge, which was constructed for the Municipality of Abu Dhabi City, has won the Global Road Achievement Award in the design category from the International Road Federation (IRF). The 2011 Global Road Achievement Awards (GRAA) programme is a worldwide contest held to identify and honour excellence, innovation and exceptional achievements in 12 key categories in the transport and infrastructure industry.
  • Award winning bridge a' masterpiece of architecture'
    March 21, 2012
    Mega project of “extreme beauty” receives top award from the IRF, writes Patrick Smith The Sheikh Zayed Bridge, which was constructed for the Municipality of Abu Dhabi City, has won the Global Road Achievement Award in the design category from the International Road Federation (IRF). The 2011 Global Road Achievement Awards (GRAA) programme is a worldwide contest held to identify and honour excellence, innovation and exceptional achievements in 12 key categories in the transport and infrastructure industry.