New Wear Crossing cables fully installed and tensioned to 50%

Structural engineering company VSL International has installed all 28 cable stays of England’s New Wear Crossing and stressed them to 50% of their design load. The next stage of stressing the cables will happen next month and be to 100% of design load. This will allow the construction team to adjust and tension them just enough to lift the bridge deck off the blue steel temporary supports that were constructed in the river to take the weight of the structure.
September 21, 2017 Read time: 3 mins
Looking good: The 28 cable stays are fully installed on the New Wear Crossing and tensioned to 50 percent.

Structural engineering company 1569 VSL International has installed all 28 cable stays of England’s New Wear Crossing and stressed them to 50% of their design load.

The next stage of stressing the cables will happen next month and be to 100% of design load. This will allow the construction team to adjust and tension them just enough to lift the bridge deck off the blue steel temporary supports that were constructed in the river to take the weight of the structure.
 
In the coming months, the temporary supports will be removed, leaving only the single central arched pylon and the bridge deck on display in the river.

Opening of the bridge is expected by spring of next year.

Finishing works, such as road surfacing, paving, lighting, the installation of railings and carrying out road markings, must all be complete before the cable stays can be finely adjusted and locked off at the end of construction.

 The 28 cable stays are installed in pairs north and south of the central pylon. Each cable stay is contained inside a white protective, plastic sheath. Inside each sheath, or tube, are between 44-77 strands, depending on a cable’s intended position on the deck, that form a single cable. They vary in length from 52-165m.

The longer the cable, the more strands there are. Each strand is the diameter of a small coin and will be tensioned to lift seven tonnes.

“People could be forgiven for thinking the bridge is very close to opening as the structure looks complete from a distance,” explained Stephen McCaffrey, project director for 1622 Farrans Construction and Victor Buyck Steel Construction, a joint venture to deliver the project on behalf of Sunderland City Council.

“We still have quite a lot to do, such as completing the road works on both sides of the river, getting the surface of the bridge deck finished and all of those additional works and safety features complete.”
 
Work began on the New Wear Crossing – Sunderland’s first bridge across the River Wear in more than 40 years – in May 2015.

The bridge become more recognisable with the 105m pylon being erected in February, the bridge deck launched across the river in spring and the installation of the cable stays during the summer.

For more information on companies in this article

Related Content

  • England’s new Sunderland Bridge renamed Northern Spire
    December 12, 2017
    The new Sunderland Bridge - on track to open in the spring - was officially named Northern Spire during a recent event on the bridge. The official naming followed a week-long public vote in which 10,000 people chose their favourite name from an official list of three names. Northern Spire received almost half of the votes, according to bridge officials. The other names were Lumen Point (34% of votes) and The Prism which received 17%. The two-span cable-stayed bridge across the River Wear in northeast
  • Bridge deck launched for the New Wear Crossing, Sunderland (Video)
    March 30, 2017

    The 300m bridge deck of Sunderland’s New Wear Crossing has been successfully launched across the river.

    The 4,750tonne concrete and steel deck was resting on the south side of the River Wear from where it was inched across to touch the north side in a 20-hour operation. It had to slide through the twin arched towers of the bridge’s double pylon on its way to its final position to connect the city regions of Pallion to the south and Castletown to the north.

  • VIDEO: Sarens raises the pylon for New Wear Crossing in Sunderland
    February 13, 2017
    It was as weekend working in Sunderland city, northeast England, for global lifting specialist 8569 Sarens.

    Over the two days, the Belgian company gently raised a 1,550tonne steel pylon that will form the backbone of the New Wear Crossing – no official name yet – across the River Wear.

    General work on the two-span cable-stay bridge started on the bridge in May 2015. The structure will be supported by the single double pylon and will have four vehicle lanes, as well as dedicated cycle and pedestrian routes.
  • Sunderland’s Northern Spire bridge opens
    August 28, 2018
    Sunderland’s Northern Spire bridge with its 105m-high central A-frame pylon opens to traffic today after a four-month delay because of poor weather. The bridge opened for pedestrians and cyclists yesterday after three Sunderland-built Nissan vehicles first crossed the bridge during a ceremony to mark completion of the project. Work began in May 2015 and the bridge has been built within its allocated €129 million budget. However, poor weather conditions pushed back the opening of the bridge from this past