New tunnel contract format published

The International engineering federation FIDIC (the International Federation of Consulting Engineers) and ITA-AITES (the International Tunnelling and Underground Space Association) are jointly publishing a new form of contract for tunnelling and underground works. Called The Emerald Book, this new contract form is intended to meet developments in the fast-growing underground market sector. The new Conditions of Contract for Underground Works (The Emerald Book) is expected to be widely used. Underground cons
May 7, 2019 Read time: 3 mins

The International engineering federation FIDIC (the International Federation of Consulting Engineers) and ITA-AITES (the International Tunnelling and Underground Space Association) are jointly publishing a new form of contract for tunnelling and underground works. Called The Emerald Book, this new contract form is intended to meet developments in the fast-growing underground market sector. The new Conditions of Contract for Underground Works (The Emerald Book) is expected to be widely used. Underground construction is highly dependent on the geological, hydrogeological and geotechnical properties of the ground, influencing the methods required for the successful implementation of the works. In addition, the difficulty in predicting ground behaviour and foreseeable conditions implies an inherent uncertainty in underground construction which gives rise to contractual risks regarding construction practicability, time and cost.

These risks are addressed in The Emerald Book, launched at the World Tunnel Congress 2019 in Naples. The launch follows several years of intensive work by a joint task group of representatives of FIDIC and ITA-AITES who identified several issues that the new standard form of contract should address to promote equitable risk allocation and the effective dealing with conditions typically unforeseeable in such projects.

These issues include several key areas, all of which have been specifically addressed in the new contract. These include: allocation of risk; disclosure of all available geological and geotechnical information; inclusion of a contractual geotechnical baseline; inclusion of a tailored “Unforeseeable Physical Conditions” clause. They also include: implementation of a ground classification system and of supporting particular conditions that properly reflect the effort of excavation and stabilisation; time for completion is largely influenced by ground conditions; provision of a flexible mechanism for remuneration according to ground conditions, foreseen and unforeseen.

Take-up of the new Emerald Book contract is expected to be widespread. Commenting on the launch of the contract, FIDIC contracts committee chair Zoltán Záhonyi said: “Working together, FIDIC and ITA-AITES have created a contract that we believe, and hope will command the respect and authority of the tunnel engineering and construction sector and that both clients and contractors can use with confidence. The new Emerald Book addresses several critical areas that should lead to the smoother running of contracts in the growing tunnelling and underground works sector.”

Tarcisio Celestino, president of the International Tunnelling and Underground Space Association, commented: “The Emerald Book will bridge an important gap. Despite all the technological developments of equipment and techniques in the field, many underground construction projects end up unsuccessful because of contractual disputes. The book brings together the result of the expertise and respectability of ITA-AITES and FIDIC in the fields of contracts and specificities for underground constructions.”

Related Content

  • Electric power projects planned
    January 26, 2018
    While diesel engines continue to be developed, there is no mistaking the current plans for electric driveline projects - Mike Woof writes The growing worldwide consensus on the massive threat to humanity posed by climate change means that the need to reduce exhaust emissions from transport and construction is becoming ever more pressing. As a result, industry is changing and new solutions are being found for transport and construction that will help lower environmental impact. Although many solutions are
  • Event: PIARC World Road Congress in Prague
    December 19, 2022
    The theme ‘Together on the road again’ is apt given that the pandemic had “kept us apart for far too long”, notes PIARC, the Permanent International Association of Road Congresses, or World Road Association.
  • Challenges of NMT in Nairobi, Dar es Salaam
    September 13, 2016
    Developing safety for non-motorised transport in East Africa - Shem Oirere writes. Despite increasing national budgetary allocations for the road sector in recent years, governments in East Africa have made very low investments in non-motorised transport (NMT). This is despite the fact that both Kenya and Uganda have recently passed a policy on pedestrian and cycling safety. In Kenya, the County government of Nairobi, the country’s capital, has embraced a NMT policy, while in Uganda the government has passe
  • David Barwell suggests six steps for closing the UK funding gap
    January 11, 2019
    Six steps for closing the UK funding gap Plenty of private money is seeking UK investment opportunities. The government and the infrastructure sector in general must make projects more attractive, writes David Barwell* It is widely acknowledged that the UK faces mounting economic, environmental and social problems if the nation's infrastructure fails to meet present and future demands. Government estimates propose that almost €561 billion is required to bridge the infrastructure funding gap. As part o