New tunnel contract format published

The International engineering federation FIDIC (the International Federation of Consulting Engineers) and ITA-AITES (the International Tunnelling and Underground Space Association) are jointly publishing a new form of contract for tunnelling and underground works. Called The Emerald Book, this new contract form is intended to meet developments in the fast-growing underground market sector. The new Conditions of Contract for Underground Works (The Emerald Book) is expected to be widely used. Underground cons
May 7, 2019 Read time: 3 mins

The International engineering federation FIDIC (the International Federation of Consulting Engineers) and ITA-AITES (the International Tunnelling and Underground Space Association) are jointly publishing a new form of contract for tunnelling and underground works. Called The Emerald Book, this new contract form is intended to meet developments in the fast-growing underground market sector. The new Conditions of Contract for Underground Works (The Emerald Book) is expected to be widely used. Underground construction is highly dependent on the geological, hydrogeological and geotechnical properties of the ground, influencing the methods required for the successful implementation of the works. In addition, the difficulty in predicting ground behaviour and foreseeable conditions implies an inherent uncertainty in underground construction which gives rise to contractual risks regarding construction practicability, time and cost.

These risks are addressed in The Emerald Book, launched at the World Tunnel Congress 2019 in Naples. The launch follows several years of intensive work by a joint task group of representatives of FIDIC and ITA-AITES who identified several issues that the new standard form of contract should address to promote equitable risk allocation and the effective dealing with conditions typically unforeseeable in such projects.

These issues include several key areas, all of which have been specifically addressed in the new contract. These include: allocation of risk; disclosure of all available geological and geotechnical information; inclusion of a contractual geotechnical baseline; inclusion of a tailored “Unforeseeable Physical Conditions” clause. They also include: implementation of a ground classification system and of supporting particular conditions that properly reflect the effort of excavation and stabilisation; time for completion is largely influenced by ground conditions; provision of a flexible mechanism for remuneration according to ground conditions, foreseen and unforeseen.

Take-up of the new Emerald Book contract is expected to be widespread. Commenting on the launch of the contract, FIDIC contracts committee chair Zoltán Záhonyi said: “Working together, FIDIC and ITA-AITES have created a contract that we believe, and hope will command the respect and authority of the tunnel engineering and construction sector and that both clients and contractors can use with confidence. The new Emerald Book addresses several critical areas that should lead to the smoother running of contracts in the growing tunnelling and underground works sector.”

Tarcisio Celestino, president of the International Tunnelling and Underground Space Association, commented: “The Emerald Book will bridge an important gap. Despite all the technological developments of equipment and techniques in the field, many underground construction projects end up unsuccessful because of contractual disputes. The book brings together the result of the expertise and respectability of ITA-AITES and FIDIC in the fields of contracts and specificities for underground constructions.”

Related Content

  • World Road Association Secretary General: ‘Act now on global road infrastructure’
    May 29, 2014
    The Secretary General of the World Road Association-PIARC has stressed the need for urgent unified action to maintain international road infrastructure. Jean-François Corté, whose association unites the road administrations of 120 governments and has members, individuals, companies, authorities and organisations in over 140 countries, spoke ahead of the keenly awaited PPRS Paris 2015 Congress 22-25 February 2015, which he is chairing. Emphasising the importance of quality road infrastructure and the need
  • São Paulo State Highway Authority wins the Evonik Road Safety Award 2018
    April 23, 2019
    For more than 50 years, Evonik – a world leader in specialty chemicals and the inventor of MMA cold plastic road markings - has been at the forefront of efforts to improve road safety and disseminate best practices in the field On 18th December 2018, Evonik bestowed the 3rd edition of the “Evonik Road Safety Award” in the city of São Paulo, Brazil. The Road Safety Award is designed to support sustainable road safety initiatives, as part of the company’s corporate and social responsibility. It acknowle
  • Lessons in asset management from the US
    August 14, 2014
    Jason Bittner discusses effective strategies for implementing efficient asset management practices The Moving Ahead for Progress in the 21st Century Act (MAP-21) established a performance-based highway programme aimed at improving how Federal transportation funds are allocated. The MAP-21 programme requires state departments of transport (DOT) to develop risk-based transportation asset management plans (TAMP) for roads and bridges. This move has also refocused attention on the need for asset management in t
  • Douglas Parkes: tunnelling pioneer obituary
    June 30, 2025
    Douglas Parkes, a pioneer of modern tunnelling technology, died recently.