New Mersey gateway bridge project underway

Work is starting on the approach viaducts for the new Mersey Gateway Bridge in the UK. The project is using longest bridge-building machine in Europe, which was named during a ceremony to mark the latest key stage the Mersey Gateway Project. Most machines of this kind can only build bridge spans of up to 60m. However, the MSS for the Mersey Gateway Bridge was specially made so it is able to cast spans of up to 70m.
September 23, 2015 Read time: 2 mins
The Mersey Gateway is a key project for the area
Work is starting on the approach viaducts for the new 6126 Mersey Gateway Bridge in the UK. The project is using longest bridge-building machine in Europe, which was named during a ceremony to mark the latest key stage the Mersey Gateway Project. Most machines of this kind can only build bridge spans of up to 60m. However, the MSS for the Mersey Gateway Bridge was specially made so it is able to cast spans of up to 70m.

It has taken construction teams three months to assemble the machine. This is no mean feat considering it includes approximately 1,200 components, 3,000 actual parts, and is held together by over 60,000 bolts. Now fully built, the MSS measures an impressive 157m long and weighs around 1,700tonnes. The MSS will now build the elevated road viaducts over the Mersey Estuary on both sides of the river, beginning with the north approach viaduct from the launch site at Catalyst Trade Park in Widnes.

The construction consortium Merseylink named the movable scaffolding system (MSS) at a special launching event at Catalyst Trade Park in Widnes. Merseylink held a competition for staff to name the MSS, with the winning name ‘Trinity' submitted by Lynn Jeary, who works in the project's communications team. The name Trinity symbolises the three bridge pylons as well as the three partners in the construction joint venture - Kier Infrastructure and Overseas Limited, Samsung C&T Corporation and FCC Construcción. The name also refers to the Merseylink bridge being sponsored by three major companies - Macquarie Capital, BBGI, and FCC.

For more information on companies in this article

Related Content

  • Peri’s new MXK lightweight platform makes London debut
    July 8, 2015
    The new platform system MXK from German-based manufacturer Peri is easily assembled to suit site requirements. The flexible platform system with lightweight brackets is assembled at ground level, using lightweight components – scaffold support bracket stop-end rails, guardrail posts, the scaffold deck and the side mesh barriers PMB. Flexibility is the key, said Peri UK managing director Alasdair Stables during an indoor demonstration day held in the docklands area of the UK capital London. The object
  • Sunderland’s Northern Spire bridge opens
    August 28, 2018
    Sunderland’s Northern Spire bridge with its 105m-high central A-frame pylon opens to traffic today after a four-month delay because of poor weather. The bridge opened for pedestrians and cyclists yesterday after three Sunderland-built Nissan vehicles first crossed the bridge during a ceremony to mark completion of the project. Work began in May 2015 and the bridge has been built within its allocated €129 million budget. However, poor weather conditions pushed back the opening of the bridge from this past
  • Sunderland’s Northern Spire bridge opens
    August 28, 2018
    Sunderland’s Northern Spire bridge with its 105m-high central A-frame pylon opens to traffic today after a four-month delay because of poor weather. The bridge opened for pedestrians and cyclists yesterday after three Sunderland-built Nissan vehicles first crossed the bridge during a ceremony to mark completion of the project. Work began in May 2015 and the bridge has been built within its allocated €129 million budget. However, poor weather conditions pushed back the opening of the bridge from this past
  • Sunderland’s Northern Spire bridge opens
    August 28, 2018
    Sunderland’s Northern Spire bridge with its 105m-high central A-frame pylon opens to traffic today after a four-month delay because of poor weather. The bridge opened for pedestrians and cyclists yesterday after three Sunderland-built Nissan vehicles first crossed the bridge during a ceremony to mark completion of the project. Work began in May 2015 and the bridge has been built within its allocated €129 million budget. However, poor weather conditions pushed back the opening of the bridge from this past