New bridge for Komarno and Komarom

Hungarian construction companies Hidepito and Meszaros es Meszaros have won a tender for a new bridge over the Danube River between Slovakia and Hungary.
May 31, 2017 Read time: 2 mins
Hungarian construction companies Hidepito and Meszaros es Meszaros have won a tender for a new bridge over the Danube River between Slovakia and Hungary.


The 600m bridge will connect the Slovakian town of Komarno and the Hungarian town of Komarom. The deal is worth just over €91 million and construction will take 33 months, according to Hungarian media.

The project has suffered several delays because of changes to procurement rules in Hungary which has pushed back completion from mid-2019 to sometime in 2020 after 33 months of construction.

The two cities, although divided by the Danube, have at times been one city under various central European kingdoms.

In March last year, the European Commission approved around €100 million towards the estimated €117 million for the project. Hungary will get €52.5 million and Slovakia will receive €47.6 million under the EU's Connecting Europe Facility.

Construction will start by the end of this year. The project was delayed temporarily by changes to procurement rules in Hungary. The bridge is expected to be complete in the second quarter of 2019.

Komárno is Slovakia's principal port on the Danube. It is also the centre of the Hungarian community in Slovakia, which makes up around 60% of the town's population.

Hungary’s Komárom and Slovakia’s Komárno are also connected by a more recently built so-called lifting bridge.

In 1892 Komárom and the then town of Újszőny were connected by an iron bridge and in 1896 the two towns were united under the name Komárom within the Austro-Hungarian empire. But after the empire was split, the towns developed separately in Hungary and Czechoslovakia.

Related Content

  • New Danube crossing linking Hungary and Slovakia
    February 2, 2016
    Construction work for a new bridge spanning the Danube River and linking Hungary and Slovakia has been delayed. The work will now commence on the project in September 2016. The new bridge will connect the town of Komarom in Hungary with Komarno in Slovakia. The project was delayed temporarily by changes to procurement rules in Hungary. The bridge is expected to be complete in the second quarter of 2019 and a portion of the funding for the new bridge will be provided by EU sources.
  • New Slovakia-Hungary bridge crossing
    June 7, 2019
    A new bridge connecting Slovakia with Hungary is under construction at present. Costing €117 million, the bridge spans the River Danube connecting Komarno in Slovakia with Komarom in Hungary. The project has been delayed but the bridge should be ready for traffic in 2020. Funding for the project is being provided by the EU and is being directed through the Slovakian Government and the Hungarian Government.
  • Budapest’s Széchenyi Chain Bridge to reopen
    November 29, 2022
    The 380m-long suspension bridge in the Hungarian capital was built between 1839 and 1849 and was the first permanent bridge connecting the towns of Buda and Pest, lying on opposite banks of the Danube River.
  • Budapest’s Széchenyi Chain Bridge reopens
    December 22, 2022
    Although open, for the time being only buses, taxis, bicycles and motorcycles can use the famous 19th century bridge that links Buda and Pest which make up the Hungarian capital.