New bridge installed in UK over busy rail line

Work to install a new bridge for the UK’s busiest rail freight line has been carried out over the A160 at the Port of Immingham. The project forms part of the Port of Immingham Improvement Scheme, a €118.15 million (£88.4 million) series of works being carried out on behalf of Highways England. The project involves upgrading 5km of the A160 from single carriageway to dual carriageway, and constructing a number of new structures. Because of the volume of rail traffic using the stretch of track, the new bridg
January 12, 2016 Read time: 2 mins
Work to install a new bridge for the UK’s busiest rail freight line has been carried out over the A160 at the Port of Immingham. The project forms part of the Port of Immingham Improvement Scheme, a €118.15 million (£88.4 million) series of works being carried out on behalf of 8100 Highways England. The project involves upgrading 5km of the A160 from single carriageway to dual carriageway, and constructing a number of new structures. Because of the volume of rail traffic using the stretch of track, the new bridge had to be installed within a tight 76 hour window.

The engineering team included Costain Engineering Services and specialist contractors such as Walters, Freyssinet , Trackwork and SPI Appleton. In order for the installation to be completed within the designated time, the team had to carry out extensive planning beforehand.

The bridge weighed in at just under 4000tonnes and was slid into place using the Autofoncage method, which utilises four large strand jacks. These jacks push the bridge as they pull against the resistance of the strands, which are fixed into the guide raft and a thrust wall.

The team used 3D and 4D Building Information Modelling which allowed them to visualise, plan and share every piece of information with the wider team, clients and stakeholders. In addition to the 4D modelling, the team also completed a Quantative Schedule Risk Assessment, which helped to identify key areas which needed special attention.

No major civil engineering project comes without its challenges and for this project the stability of the old rail embankment caused the biggest hurdle by extending the period the team needed to carefully backfill the structure. The team overcame this challenge and worked closely with Network Rail to manage the completion of the works within the allocated time.

As well as carrying the country’s busiest freight railway line, the new bridge will allow the new highway link to pass underneath it.

For more information on companies in this article

Related Content

  • UK motorway bridge work
    June 10, 2025
    A new bridge now spans the UK’s busy M6 motorway.
  • Formwork innovations help bridge building
    July 7, 2015
    A series of formwork developments are helping with challenging bridge construction projects around the world - Mike Woof writes In the Polish city of Krakow, a cost-effective cable stayed bridge is being constructed using a balanced cantilever technique. The current expansion of the Krakow metropolitan railway network (KST) requires the building of a crossing of the Krakow-Plaszow railway junction. Ensuring that daily rail operations remained unaffected during the construction of the 252m long crossing w
  • Maybe Hire takes on Whorlton Bridge
    March 14, 2025
    For refurbishment of the old English bridge, a temporary cable crane structure - designed by CaSE Civil & Structural Engineering - used a range of Mabey Hire’s propping equipment, including the Mass 50, System 160 and Mat 125 products.
  • Towers of power: California’s Gerald Desmond Bridge Replacement
    May 8, 2019
    Challenging ground conditions meant a design rethink - and some engineering firsts - for California’s Gerald Desmond Bridge Replacement Project* The Port of Long Beach on Terminal Island south of Los Angeles is the second-busiest container port in the US. It handles around 15% of all imported goods, much of it with Asia. As the Port of Long Beach was growing in importance over the past half century, the 51-year-old Gerald Desmond Bridge has faithfully been delivering thousands of daily commuters to wo